Construction method for reserved steel bars of top of mid-partition in tunnel engineering
A technology for reserving steel bars and tunnel engineering, which is used in tunnels, tunnel linings, and earthwork drilling to achieve the effects of improving construction speed, reducing time, and reducing the high shrinkage of vault concrete.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0022] A construction method for reserving reinforcing bars at the top of a middle partition wall in a tunnel engineering of the present invention as shown in the accompanying drawings, comprising the following steps:
[0023] (1) Make multiple sets of prefabricated parts, and carry out initial support layer 2 construction on the free surface of tunnel surrounding rock 1 at the same time;
[0024] Each group of making prefabricated parts includes the following steps: (a) Arranging a plurality of pre-embedded steel bars 5 of the right-angled middle partition wall at intervals in the longitudinal direction at the reinforcement processing site outside the cave, and connecting them to form a group of pre-embedded steel bars for the middle partition wall through longitudinal connecting bars (b) two groups of intermediate wall pre-embedded reinforc...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 

