Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Post-pouring tape construction method for large-area roof buildings with main girders passing through post-pouring tape

A construction method and technology of post-pouring tape, which is applied to the preparation of building components on site, construction, building structure, etc., can solve the problems of long construction period, high project cost, unusable lower space, etc., to shorten the construction period, Effects of cost saving, good social value and economic value

Active Publication Date: 2019-07-23
SHANGHAI URBAN CONSTR DESIGN RES INST GRP CO LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] This causes the lower space of the building to be unusable during the construction of the post-cast belt, resulting in problems such as high project cost and long construction period.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Post-pouring tape construction method for large-area roof buildings with main girders passing through post-pouring tape
  • Post-pouring tape construction method for large-area roof buildings with main girders passing through post-pouring tape

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0021] Such as figure 1 As shown, the post-casting belt construction method of the large-area roof building where the main beam passes through the post-casting belt, the steps are as follows:

[0022] a. Pre-embed the lifting ring at the position where the main beam 3 is located at the post-casting belt 5;

[0023] b. Concrete is poured, and the pre-embedded suspension ring is exposed on the position where the main beam 3 is located at the post-casting belt;

[0024] c. Temporary supports 1 are set on both sides of the post-casting belt 5;

[0025] d. Erection of temporary steel beams 2 on two temporary supports 1;

[0026] e. When the strength of the main beam 3 on both sides of the post-cast belt 5 meets the design requirements, a steel cable 4 is fixed between the temporary steel beam 2 and the embedded lifting ring.

[0027] The present invention is based on the method of setting pre-embedded suspension rings at the position where the concrete main girder 3 passes throu...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a post-cast strip construction method of a large area roofing building with a main beam passing through a post-cast strip. The construction method includes the following stepsthat lifting rings are pre-buried in the positions, located on the post-cast strip (5), of the main beam (3); concrete is poured, and the pre-buried lifting rings are exposed in the position, locatedon the post-cast strip, of the main beam (3); two temporary supports (1) are arranged on the two sides of the post-cast strip (5); a temporary structural steel beam (2) is erected on each of the two temporary supports (1); and after the strength of the portions, located on the two sides of the post-cast strip (5), of the main beam (3) meets design requirements, wire ropes (4) are installed betweenthe temporary structural steel beams (2) and the pre-buried lifting rings to fix. According to the post-cast strip construction method, in the period of waiting for pouring of the post-cast strip (not less than 28 days in general according to the specifications), a construction space below the main beam (3) can be impervious to an original erected scaffold, multiple working procedures can be conducted simultaneously, the building efficiency is improved, and the construction cost is reduced.

Description

technical field [0001] The invention relates to the technical field of house construction, in particular to a construction method of a post-casting belt for a large-area roof building in which main girders pass through the post-casting belt. Background technique [0002] The post-pouring belt is a temporary part set at the corresponding positions of the foundation floor, wall and beam in order to prevent the harmful cracks that may occur in the cast-in-place reinforced concrete structure due to uneven shrinkage or uneven settlement during construction. construction joints. [0003] In the prior art, the construction method of the post-casting belt is to support the concrete on both sides of the post-casting belt from bottom to top, and the lower support system can only be removed after the construction of the post-casting belt is completed and the concrete reaches the design strength. [0004] This causes the lower space of the building to be unusable during the constructio...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G11/48E04G11/50
Inventor 梁锋裘珍妮唐文周刘书孙炎
Owner SHANGHAI URBAN CONSTR DESIGN RES INST GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products