Field construction material intelligent management method based on BIM

A technology of intelligent management and on-site construction, applied in the field of building construction management, can solve problems such as rising costs and delays in construction schedules, and achieve the effect of standardized management and reasonable procurement

Active Publication Date: 2018-05-08
CHINA CONSTR SENVENTH ENG BUREAU INSTALLATION ENG
View PDF6 Cites 16 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, the planned entry and reasonable and dynamic management of materials is always a difficult point in project management. Due to untimely and unreasonable material procurement, entry and stacking, the construction period is often delayed or the cost rises

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Field construction material intelligent management method based on BIM
  • Field construction material intelligent management method based on BIM

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0014] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0015] Such as figure 1 As shown, a BIM-based on-site construction material intelligent management method includes a construction site material information unit, a monitoring unit, a BIM standard data unit, an enterprise server, and an intelligent terminal; the construction site material information unit includes an incoming material information collection module and the planned material module; the incoming material information collection module uploads the a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a field construction material intelligent management method based on BIM. A system according to the method comprises a construction field material information unit, a monitoring unit, a BIM standard data unit, an enterprise server and an intelligent terminal. The construction field material information unit comprises a field entering material information acquisition moduleand a planned material module. The field entering material information acquisition module uploads the actual number and the actual quality information of the material which enters the construction field to the enterprise server. The planned material module uploads the planned number and the planned quality which are required by the construction field to the enterprise server. According to the field construction material intelligent management method, BIM technology is combined with other technology, construction engineering management factors such as information acquisition, information transmission and information processing, engineering factor management system, monitoring identification system, automatic counting system, Internet technology and Internet-of-things technology are combined. Finally accurate, in-time and reasonable purchasing, field entering and management of main materials are finally realized. Furthermore dynamic adjustment is performed according to the actual requirement, thereby realizing refinement of main materials of the project.

Description

technical field [0001] The invention belongs to the technical field of building construction management, and in particular relates to a BIM-based intelligent management method for on-site construction materials. Background technique [0002] An engineering project is not only completed and put into production and use, but also to achieve reasonable economic and social benefits during the construction process, which not only depends on the input of raw materials, manpower, machinery, and capital, but also depends on the reasonable use of the above resources. Planning, deployment and dynamic adjustment, intensification and information management of construction enterprises are becoming increasingly important. [0003] Materials are the main resources in project construction and the basic elements of buildings. Strengthening material management is the key factor to realize project completion on schedule. However, the planned entry and reasonable and dynamic management of mate...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06
CPCG06Q10/06313
Inventor 靳书平郝少权孙红伟张东升史增强
Owner CHINA CONSTR SENVENTH ENG BUREAU INSTALLATION ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products