A construction method and technology for shield tunneling, which are applied to tunnels, fillings, earth-moving drilling and mining, etc., can solve the problems of construction organization and material transportation organization, long concrete curing time, poor construction operation environment, etc., and shorten the construction time. The effect of reducing the construction period, reducing construction safety risks, and improving construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0046] 1. Production of prefabricated blocks for tunnel bottom backfill
[0047] (1) The backfill prefabricated block at the bottom of the tunnel is prefabricated in advance with high-precision steel molds in the factory. The structural section is crescent-shaped, the lower surface is arc-shaped, concentric with the surface of the shield segment, and the upper surface is horizontal. It is a concrete solid structure; it is assembled and constructed synchronously with the shield tunnel segment to speed up the construction speed of the backfill structure at the bottom of the tunnel.
[0048] (2) The width of the prefabricated block is 4.29m, and the height is 0.61m, so as to meet the walking of the supporting trolley behind the shield machine; in order to facilitate the assembly and fixation of the prefabricated structure, four supports are set on the lower surface of the prefabricated block, and the size is 500mm (L) × 300mm (width) × 50mm (height), reserve a 50mm-thick gap in t...