Tunnel Excavation Progress Simulation Method Considering Construction Abnormalities
A simulation method and abnormal technology, applied in the direction of design optimization/simulation, instrumentation, data processing applications, etc., can solve the problems of large impact on the overall progress, instability, and non-discriminatory construction abnormal progress simulation, etc., to achieve simple algorithms, good Lu sticky effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0061] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0062] A tunnel excavation progress simulation method considering abnormal construction proposed by the present invention comprises the following steps:
[0063] A) The tunnel excavation cycle process is decomposed into drilling work unit, charge work unit and blasting waiting work unit;
[0064] B) using the box-and-whisker theory to separate the normal duration and abnormal duration of each working unit of tunnel excavation for the drilling work unit, charging work unit and blasting waiting work unit,
[0065] C) using mathematical statistics to deduce the distribution form and distribution parameters of the normal duration and abnormal duration of the drilling work unit, charge work unit and blasting waiting work unit;
[0066] D) Use the Monte Carlo simulation method to independently sample the drilling work unit, charge work uni...