Small-watershed water body non-point source pollution recovery and control system and construction method thereof
A non-point source pollution, small watershed technology, applied in chemical instruments and methods, biological water/sewage treatment, water/sludge/sewage treatment, etc. problems, to achieve the effect of purifying water quality and good economic benefits
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0034] The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention. If no specific technique or condition is indicated in the examples, it shall be carried out according to the technique or condition described in the literature in this field.
[0035] Example 1 The control experiment of COD, TN, TP by the surface source pollution restoration control system of small watershed water body
[0036] Select a small watershed in Dongting Lake District, Hunan Province, with a watershed area of 23.8km 2 , according to the following steps to build a small watershed non-point source pollution restoration control system:
[0037] (1) Select a site to build a dam. According to the measurement of the pollution of the entire watershed, determine a suitable interception point in the concentrated area where the water quality reaches V class or above; Water outlets are set on the side and in the middle, and gates are ...
Embodiment 2
[0044] Example 2 Control experiment of COD, TN, TP by the non-point source pollution restoration and control system of small watershed water
[0045] Select a small watershed in Dongting Lake District, Hunan Province, with a watershed area of 12.6km 2 , according to the following steps to build a small watershed non-point source pollution restoration control system:
[0046] (1) Select a site to build a dam, and determine the appropriate interception point according to the pollution situation of the entire watershed;
[0047] (2) Reconstruction of farmland and rivers, transforming farmland and rivers into sedimentation ponds, planting ponds and artificial wetlands, the depth of sedimentation ponds is 0.5m, the depth of planting ponds is 1.2m, the depth of artificial wetlands is 0.5m, and the thickness of biochar at the bottom of each pond is 5cm ;
[0048] (3) Animal and plant breeding, plant Gorgon fruit in the sedimentation pond, Xianglian in the planting pond, 3000 carp...
Embodiment 3
[0052] Example 3 Control experiment of COD, TN and TP by the non-point source pollution restoration and control system of small watershed water
[0053] Select a small watershed in the Dongting Lake area of Hunan Province, with a watershed area of 28.4km2 , according to the following steps to build a small watershed non-point source pollution restoration control system:
[0054] (1) Select a site to build a dam, and determine the appropriate interception point according to the pollution situation of the entire watershed;
[0055] (2) Reconstruction of farmland and rivers, transforming farmland and rivers into sedimentation ponds, planting ponds and artificial wetlands, the depth of sedimentation ponds is 0.8m, the depth of planting ponds is 1.5m, the depth of artificial wetlands is 0.5m, and the thickness of biochar at the bottom of each pond is 5cm ;
[0056] (3) Animal and plant breeding, plant Gorgon fruit in the sedimentation pond, Xianglian in the planting pond, 3000...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com