A tower-anchor-pier-anchor combined rapid construction method for a self-anchored suspension bridge
A technology of self-anchored suspension bridge and construction method, which is applied in the direction of suspension bridge, bridge construction, construction, etc., can solve the problems of long construction period and large traffic interference of the main span, and achieve the advantages of fast construction progress, high thrust resistance stiffness and low cost Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0075] This embodiment provides a kind of tower-anchor-pier-anchor combined rapid construction method of a self-anchored suspension bridge, such as Figure 1 to Figure 9 As shown, the method adopts the combination of the tower beam thrust connection device 13 and the pier beam thrust connection device 14 to build a self-anchored suspension bridge;
[0076] The structures of the tower beam thrust connection device 13 and the pier beam thrust connection device 14 are identical;
[0077] The method includes the following steps:
[0078] Step 1, synchronous construction of side span main girder 6 and bridge tower 7;
[0079] Step 1.1, carry out foundation treatment to the foundation of bridge tower 7 and bridge pier 12, construct bridge tower 7 foundation, bridge pier 12 foundation, bridge tower 7 and bridge pier 12;
[0080] Step 1.2, set the side-span support 11, construct the side-span main beam 6 on the support 11, and complete the construction of the side-span main beam 6; ...