Method for calibrating roller-gap of slab casting machine
A calibration method and roll gap technology are applied in the field of roll gap calibration of slab casting machines, which can solve the problems of slab quality and affecting the actual size of the roll gap.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] Such as figure 1 As shown, the calibration method of the slab caster roll gap of the present embodiment is characterized in that it comprises the following steps:
[0029] S01, measuring the roll gap of the upper and lower rolls to obtain the roll gap value a;
[0030] When measuring the roll gap value a for the first time, it is necessary to ensure the accuracy of the roll gap value a. At this time, the slab caster should be in an offline state, and the upper and lower rolls are neither stressed nor heated. Various tools can be used to measure the roll gap. In this embodiment, a hand-held roll gap meter can be used to measure the roll gap value a conveniently and quickly.
[0031] S02. Apply force to the upper and lower rolls, measure the roll gap of the upper and lower rolls, obtain the roll gap value e, and calculate the deviation value b between e and a;
[0032] After the actual roll gap value is measured, pressure should be applied to the upper and lower rolls, ...
Embodiment 2
[0045] As another embodiment of this specification, in this example, the maximum section of the steel plate cast by the slab caster is 230×1600 mm, and after measuring the actual roll gap value of 230 mm, a load simulator is used to support the upper and lower sections of the segment Roll, apply a force of 45000N to the upper and lower rolls, and then use a hand-held roll gap meter to measure the roll gap e, and calculate the deviation between e and a to be 0.3mm; after removing the force on the upper and lower rolls, use a load simulator A force of 40,000N is also applied to the sector frame, and after the roll gap value f is measured with a hand-held roll gap meter, the calculated deviation between f and a is 0.2mm.
[0046] After a casting is completed, set 1 hour as a time node. It takes 20 hours from the completion of casting to complete cooling. The start time of the next casting is 2 hours from the end of the previous one. At this time, the deviation value d is a fixed v...
Embodiment 3
[0049] As another embodiment of this specification, in this example, the maximum section of the steel plate cast by the slab caster is 230×1600 mm, and after measuring the actual roll gap value of 230 mm, a load simulator is used to support the upper and lower sections of the segment Roll, apply a force of 45000N to the upper and lower rollers, and then use a hand-held roll gap meter to measure the roll gap e, and calculate the deviation between e and a to be 0.2mm; after removing the force on the upper and lower rollers, use a load simulator A force of 40,000N is also applied to the sector frame, and after the roll gap value f is measured by a hand-held roll gap meter, the calculated deviation between f and a is 0.3mm.
[0050] After one casting is completed, set 1 hour as a time node. It takes 20 hours from the completion of casting to complete cooling. The start time of the next casting is 22 hours from the end of the previous one. At this time, the linear equation between t...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 
