Back break control method for tunnel

A control method, over- and under-excavation technology, applied in tunneling, earthwork drilling, blasting, etc., can solve problems such as under-excavation and over-excavation, and achieve the effects of quality and safety assurance, fast process cycle, and effective control of construction costs

Active Publication Date: 2019-08-16
陕西路桥集团有限公司
View PDF4 Cites 19 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to provide a tunnel overbreak and underbreak control method to solve the disadvantages of underbreak and overbreak that are often encountered during the full-section excavation process of traditional tunnel blasting.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Back break control method for tunnel
  • Back break control method for tunnel
  • Back break control method for tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 2

[0049] Advanced geological prediction or tunnel advanced geological prediction is to make advanced prediction of the surrounding rock and formation conditions in front of and around the tunnel face during tunnel excavation. Relying on short- and medium-distance geological radar prediction and long-distance TSP reflection wave method, the accuracy of judging the trend of faults or the trend of weak interlayers is not high. The drilling and blasting scheme designed without fully grasping the geological conditions has serious overbreak and underbreak phenomena, and the blasting effect cannot be guaranteed.

[0050] Therefore, this embodiment conducts on-site investigation and supplementary verification on the basis of advance forecast. Due to the extremely frequent geological changes in the fold area, there are completely different surrounding rock characteristics between blasting cycles, and even between the left and right sides, upper and lower parts of the excavation face of t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a back break control method for a tunnel. The method comprises the following steps: first, further optimizing original blasting parameters according to a surrounding rock condition determined by advance geology forecast and construction site investigation; then letting out a hole distributing position accurately according to the optimized blasting parameters; and finally, drilling, cleaning the hole, and charging an explosive, and connecting a detonating network to blast. The blasting parameters of an excavated smooth face of a conventional stone tunnel is optimized according to the type of the surrounding rock determined jointly by advance geology forecast combined with construction site investigation around by finely adjusting the drilling parameter and the charging structure by means of existing common materials such as a fire work material and a water bag, so that the blasting quality of full face excavation of the tunnel is improved, a back break phenomenonin conventional full face blasting of the tunnel is reduced to the maximum extent, and targets that the blasting effect is good, the quality safety is guaranteed, the construction cost is controlled effectively and the steps are circular and convenient in sandy slate tunnel excavation penetrating a belt of folded strata are achieved.

Description

technical field [0001] The invention relates to the field of tunnel construction, in particular to a method for controlling over- and under-excavation of tunnels. Background technique [0002] For silty slate geological tunnels, over- and under-break control during construction, especially the quality control of over-break, is the biggest factor affecting the quality and safety of tunnel construction, construction progress, and construction cost. This requires us to reasonably select the excavation method and blasting parameters during the tunnel construction process, scientifically and accurately judge the changes in the surrounding rock and adjust the relevant parameters in a timely manner, so as to achieve the smooth blasting effect as the goal, and reduce the over- and under-excavation during the tunnel excavation construction. Adverse effects are reduced to the minimum level, so as to realize the effective control of tunnel construction quality, safety, schedule and cos...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): F42D3/04E21D9/00
CPCE21D9/006F42D3/04
Inventor 马雄伟舒霖房会斌张健王晶
Owner 陕西路桥集团有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products