[0044] The specific implementation of the method for transforming a single-bus operating transformer station of the present invention will be described in detail below in conjunction with the accompanying drawings.
[0045] see figure 1 , 2 , during transformation, move the load of the No. 2 main substation to the No. 1 main substation; disconnect the circuit breaker between the No. 2 main substation and the single busbar; The bus isolating switch of the section corresponding to the main transformer No. Add the related equipment of the first section of double busbar, and all the tests are qualified; connect the No. circuit breaker; make the No. 2 main substation interval equipment energized; check the phases of the No. No. main substation;.
[0046] The double-dot dash line in the figure is the power-off interval, and the operation is carried out in the power-off interval, and the other uninterrupted power intervals work as usual.
[0047] see image 3 , 4. Move the load...