Rock engineering damaged surface ecological remediation method
A technology of ecological restoration and engineering, applied in the fields of land preparation, infrastructure engineering, excavation, etc., can solve problems such as the inability to prevent soil loss
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0020] A method for ecological restoration of rock engineering wounds, specifically comprising the following steps:
[0021] S1. The slope surface is divided by lattice beams. At the same time, the lattice beams are fixed on the slope surface by anchors. The cross-sectional area of the protective lattice beams is 250mm*400mm, along the longitudinal direction of the slope lattice beams and The horizontal interval is 3m, three spans constitute one beam, and a 20mm gap is set between two adjacent beams, and fillers are set in the gaps, and the fillers are specifically asphalt hemp silk, and two rows of anchors are arranged along the slope, and the anchors The length of the borehole is 4m, the diameter of the borehole is 100mm, and the angle of incidence is 37°. Before performing the S1 step, it is necessary to use a soil compactor to compact the slope;
[0022] S2. Rows and intercepting ditches are set at the bottom and top of the slope respectively. Prestressed anchor cables a...
Embodiment 2
[0029] A method for ecological restoration of rock engineering wounds, specifically comprising the following steps:
[0030] S1. The slope surface is divided by lattice beams. At the same time, the lattice beams are fixed on the slope surface by anchors. The cross-sectional area of the protective lattice beams is 250mm*400mm, along the longitudinal direction of the slope lattice beams and The horizontal interval is 4m, three spans constitute one beam, and a gap of 25mm is set between two adjacent beams, and fillers are set in the gaps, and the fillers are specifically asphalt hemp silk, and three rows of anchors are arranged along the slope. The length of the borehole is 4-7m, the diameter of the borehole is 108mm, and the angle of incidence is 37°. Before the S1 step, it is necessary to use a soil compactor to compact the slope;
[0031] S2. Rows and intercepting ditches are set at the bottom and top of the slope respectively. Prestressed anchor cables and concrete frame be...
Embodiment 3
[0038] A method for ecological restoration of rock engineering wounds, specifically comprising the following steps:
[0039] S1. The slope surface is divided by lattice beams. At the same time, the lattice beams are fixed on the slope surface by anchors. The cross-sectional area of the protective lattice beams is 250mm*400mm, along the longitudinal direction of the slope lattice beams and The horizontal interval is 5m, three spans constitute one beam, and a 30mm gap is set between two adjacent beams, and fillers are set in the gaps, and the fillers are specifically asphalt hemp silk. The anchors are arranged in 4 rows along the slope, and the anchors The length of the borehole is 7m, the diameter of the borehole is 115mm, and the angle of incidence is 37°. Before the S1 step, it is necessary to use a soil compactor to compact the slope;
[0040] S2. Rows and intercepting ditches are set at the bottom and top of the slope respectively. Prestressed anchor cables and concrete f...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com