A direct heating device using abandoned mine shaft and its construction method
A heating device and mine technology, applied in the application, heating method, household heating and other directions, can solve the problems of easy blockage of heating devices and environmental threats, and achieve the effects of good applicability, convenient construction and easy installation.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] refer to Figure 1-7 , which is the first embodiment of the present invention, provides a direct heating device using an abandoned mine, which includes a pipe assembly 1, a connection assembly 2, a protection assembly 3, a fixing assembly 4, a water pump 5 and a plate heat exchanger 6. Wherein, the connection assembly 2 includes a flange seat 21, a flange head 22 and a fastener 23, the flange seat 21 and the flange head 22 are respectively arranged at both ends of the pipe assembly 1, and the end surfaces of the two can cooperate with each other, The fastener 23 connects the flange seat 21 and the flange head 22 in one body; the pipe assembly 1 includes a steel pipe 11, a hose 12 and a conduit 13, all of which can be connected to each other through the connection assembly 2 provided at the end. 11 is bidirectionally distributed in the shaft of the mine, while the hose 12 is distributed in the shaft and roadway of the mine, one end of which is connected to the end of the...
Embodiment 2
[0052] Different from Embodiment 1, the construction method for the direct heating device includes the following construction steps:
[0053] S1: scheme design, design a complete heating scheme according to the heating demand and the heat supply of the mine;
[0054] S2: For specific construction, the steel pipe 11 is installed, and the pipes are arranged vertically and bidirectionally along the inner wall of the shaft, divided into water inlet pipes and water outlet pipes, and fixed by U-shaped rods 41;
[0055] S3: hose installation, the vertical part of the hose 12 on the inner wall of the shaft needs to be installed first, and the buoyancy air bag 32 and the U-shaped soft rod 42 are arranged in sequence;
[0056] S4: Select two groups of roadways located at different depths, and check the area where the hose 12 is laid in the roadway, and remove obstacles;
[0057] S5: After the investigation and cleaning are completed, a sand cushion 31 is installed at the bottom of the ...
PUM