Track panel type long sleeper embedded ballastless track and construction method thereof
A technology of long-bolster buried, ballastless track, applied in the field of rail transit, can solve the problems of low construction efficiency, long construction period and high construction cost, and achieve the effects of improving installation efficiency, shortening construction period, strong integrity and bearing capacity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0060] The present embodiment provides a long-row rail sleeper buried ballastless track, such as figure 1 and figure 2 Shown, comprises a base plate 6, and is provided in situ on the base channel deck plate 4, 6, the pouring channel 4 in the deck unit length between three sleepers embedded in a plurality of said sleeper 3, a plurality of sleeper track panel formed by the connection mechanism, the rail-row long sleeper buried ballastless track comprising a rail mounted on a further 1 to 3 and sleeper fastening system (not shown), fastening the rail system in a fixed on the rail. A plurality of connection mechanism using the sleepers 3 are connected integrally to form a track panel, unitary structure, to solve the track panel construction assembly and adjustment positioning site present in the prior art when the sleepers embedded in a cast channel 3 deck 4 inefficiencies, comprising a plurality of one-time installation sleeper sleeper track panel 3, since the relative position has b...
Embodiment 2
[0072] The present embodiment provides a construction method for long-row rail sleeper buried ballastless track, such as Figure 1-6 , In the construction of such long-row rail sleeper buried ballastless track in the embodiment of Example 1, the main construction comprises:
[0073] a, factory prefabricated concrete sleeper 3, 31 and truss reinforced sleepers 3 are assembled into rows rail sleeper;
[0074] B, according to the measurement data track work, pouring concrete base plate 6 and the retaining groove 61 at the construction site, after the completion of pouring conservation;
[0075] C, the elastic cushion 51 laid on the retaining groove 6, and the laying of the separating layer 2 and the stopper surface of the surface recess 61 of the base plate 6;
[0076] d, erection sleeper track panel, and adjust, after pouring the concrete track bed board formwork, pouring channel thereby forming deck 4 and the stopper boss 5, while the deck 4 and the channel stopper cast bosses 5 con...