A prefabricated pipe internode connecting device and a construction method for its application
A technology for connecting devices and pipe joints, used in shaft equipment, bolt installation, earthwork drilling, etc., can solve the problems of inability to penetrate, easy to block, etc., and achieve the effect of reducing friction and improving bending resistance.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] Embodiment 1: as figure 1 and Figure 4 As shown, a connection device between prefabricated pipe sections includes a connecting piece, the connecting piece is passed through the reserved channel 6 on the prefabricated pipe section 5 and the connecting piece passed through the adjacent prefabricated pipe section 5 is detachably connected; An adjustment mechanism is sleeved on the connecting piece, and the adjustment mechanism cooperates with the reserved channel 6 on the prefabricated pipe joint.
[0040] The connecting piece includes a flexible connecting rope, the length of the flexible connecting rope is slightly longer than the longitudinal length of the pipe joint, and its diameter is smaller than the diameter of the reserved channel. The flexible connecting rope is passed through the reserved channel 6 on the prefabricated pipe joint 5 and The flexible connecting rope passing through the reserved channel 6 on the adjacent prefabricated pipe section 5 is detachably...
Embodiment 2
[0043] Embodiment 2: A construction method using a prefabricated pipe internode coupling device, comprising the following steps:
[0044] S1. Prefabricated pipe internode connection device preparation: firstly prepare sufficient flexible connectors, fixedly sleeve the tube capsule on each flexible connector, and carry out trial docking of each flexible connector;
[0045] S2. Construction of the first section of prefabricated pipe joints: if Figure 5 and Figure 6As shown, after the first section of the prefabricated pipe section is assembled in place in the tunnel, the flexible connector is inserted into the reserved channel 6 on the first section of the prefabricated pipe section simultaneously, and the flexible connector is passed through the reserved channel to leave the connecting joint. Then use the expansion tube to inflate or fill the reserved channel 6 with liquid, or use other elastic tubes to self-adaptively fill the reserved channel 6 driven by the flexible conne...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


