Oil-gas drilling concrete bridge leaking stoppage process method
A technology of oil and gas drilling and process method, which is applied in the direction of earthwork drilling, wellbore/well components, sealing/isolation, etc. It can solve problems such as repeated leakage, karst caves are difficult to play the role of plugging, and plugging failure, etc., to achieve good application Prospects, the effect of reducing the risk of re-leakage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0018] The oil and gas drilling concrete bridging plugging process method of this embodiment is suitable for the situation that the concrete required for plugging cannot be bridging in the pumping drilling tool, wherein the maximum particle size of the crushed stone is not more than 10 mm.
[0019] The specific steps are:
[0020] A. Concrete preparation: Use a mixer truck or a mixer to prepare the concrete required for plugging with gravel;
[0021] B. Concrete pumping: Use a concrete pump truck or a concrete pump to pump the prepared concrete through the drilling tool to the location of the well leakage and squeeze it into the leakage channel to stop the leakage.
Embodiment 2
[0023] The oil and gas drilling concrete bridging plugging process method of this embodiment is suitable for preventing the concrete from blocking the drilling tool and causing complicated situations, wherein the maximum particle size of the crushed stone does not exceed 30 mm, and the specific steps are as follows:
[0024] A. Use a mixer truck or a mixer to prepare drilling fluid thick slurry and gravel to form bridging plugging slurry;
[0025] B. Use a concrete pump truck or a concrete pump to send the bridging plugging slurry into the leakage channel through the drilling tool to form a bridge and reduce the leakage speed;
[0026] C. Prepare sand and cement slurry, send the sand and cement slurry to the lost channel through the drilling tool through the concrete pump, pressurize the wellhead and replace the drilling fluid thick slurry in the original bridging plugging slurry in the gaps of the bridging gravel particles, form a concrete structure.
Embodiment 3
[0028] The oil and gas drilling concrete bridging plugging process method of this embodiment is applicable to the situation that the concrete required for plugging cannot be pumped by pumping drilling tools, and the specific steps are:
[0029] A. Use a mixer truck or a mixer to prepare the concrete required for plugging;
[0030] B. Concrete pump truck or concrete pump is continuously pumped into the wellbore at the wellhead of the drilling well, and then the drilling fluid is pumped into the drilling fluid through the drilling pump to send the concrete to the leaking position and squeeze into the leaking layer to stop the leaking.
PUM