Method for synchronously constructing deep foundation pit and near-edge foundation process
A technology of synchronous construction and deep foundation pit, which is applied in the direction of basic structure engineering, excavation, construction, etc., can solve the problems that the surrounding shallow foundation cannot be constructed, and achieve the effect of shortening the construction period, reducing the possibility, and reducing the earthwork load
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] Such as figure 1 Shown: a method for synchronous construction of deep foundation pit and adjacent foundation process, which includes the following steps:
[0023] Step 1. Geological survey:
[0024] 1.1 The surface layer of the site within the construction scope is miscellaneous fill and residual soil, followed by fully weathered granite, strongly weathered granite, and moderately weathered granite;
[0025] Step 2. Preparation before construction:
[0026] 2.1 In order to ensure the construction safety of the deep foundation, the 30m area around the foundation is used as the construction area, and it is forbidden to stack heavy loads or construct other buildings in this area;
[0027] 2.2 The excavation depth of the pipe gallery is 8.1-8.2m, and the excavation depth of the column foundation is 4.4m, which is difficult to excavate. The working surface of the pipe gallery is long, interspersed with the rainy season, and the drainage workload during the rainy and preci...