Out-of-pit ground surface settlement prediction method considering whole foundation pit excavation process in soft soil area

A technology of surface subsidence and prediction method, which is applied in the field of foundation soil survey, prediction, infrastructure engineering, etc., and can solve problems such as poor prediction effect

Active Publication Date: 2021-04-30
CHINA RAILWAY 11TH BUREAU GRP +1
View PDF5 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] Aiming at the technical problems in the prior art, the present invention provides a method for predicting surface settlement outside the pit considering the whole process of foundation pit excavation in soft soil areas, and solves the problem of poor prediction effect in the prior art

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Out-of-pit ground surface settlement prediction method considering whole foundation pit excavation process in soft soil area
  • Out-of-pit ground surface settlement prediction method considering whole foundation pit excavation process in soft soil area
  • Out-of-pit ground surface settlement prediction method considering whole foundation pit excavation process in soft soil area

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0057] Embodiment 1 provided by the present invention is an embodiment of the surface settlement prediction method outside the pit considering the whole process of foundation pit excavation in a kind of soft soil area provided by the present invention, and this embodiment includes:

[0058] Step 1: Monitor the surface settlement during the whole excavation process of the foundation pit. Based on the monitoring data, obtain the relationship function 1 between the maximum lateral settlement value of the surface outside the pit and the excavation depth, and the relationship function between the maximum lateral settlement position of the surface outside the pit and the excavation depth Number two, based on relational function 1 and relational function 2, the prediction function of the lateral settlement of the surface outside the pit considering the whole process of foundation pit excavation is obtained, and the lateral direction is perpendicular to the long side of the foundation p...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to an out-of-pit ground surface settlement prediction method considering the whole foundation pit excavation process in a soft soil area, which comprises the following steps: carrying out ground surface settlement monitoring on the whole foundation pit excavation process; based on the monitoring data, obtaining a first relation function between the transverse maximum settlement value of the out-pit surface and the excavation depth and a second relation function between the transverse maximum settlement position of the out-pit surface and the excavation depth, and based on the first relation function and the second relation function, obtaining an out-pit surface transverse settlement prediction function considering the whole foundation pit excavation process; based on the complementary error function and the transverse maximum settlement value of the ground surface outside the pit, obtaining a longitudinal settlement prediction function of the ground surface outside the pit considering the whole foundation pit excavation process; and obtaining a settlement value of any point outside the pit at any excavation stage based on a curve of the transverse settlement prediction function of the ground surface outside the pit and the longitudinal settlement prediction function of the ground surface outside the pit. On the basis of foundation pit deformation monitoring data and in combination with theoretical analysis, ground surface settlement outside a pit in the whole foundation pit excavation process can be dynamically predicted, and the reliability of foundation pit monitoring can also be evaluated.

Description

technical field [0001] The invention relates to the field of surface subsidence prediction, in particular to a method for predicting surface subsidence outside a pit considering the whole process of foundation pit excavation in soft soil areas. Background technique [0002] With the vigorous development of urban engineering construction activities, the city's demand for land resources is increasing, and more and more foundation pit projects are close to buildings, subway stations, underground pipelines, etc. It is inevitable to carry out foundation pit construction along the subway tunnel, and excavation of foundation pits in soft soil areas with dense buildings and pipelines will inevitably bring disturbances to the adjacent environment, such as causing uneven settlement of the road surface, deformation of underground pipelines, Severe cases may even cause cracking and damage to the structure. It can be seen that it is very important to accurately, quickly and easily predi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G01C5/00E02D1/00G06F17/15G06Q10/04G06Q50/08
CPCG01C5/00E02D1/00G06F17/15G06Q10/04G06Q50/08
Inventor 程康张旭东唐达昆夏明锬胡小银梅灿徐日庆甘晓露
Owner CHINA RAILWAY 11TH BUREAU GRP