Embodiment 1
[0055] Embodiment 1: as figure 1 , figure 2 , image 3 , Figure 4 , Figure 5 , Image 6 , Figure 7 , Figure 8 , Figure 9 , Figure 10 , Figure 11 , Figure 12 , Figure 13 , Figure 14 , Figure 15 , Figure 16 , Figure 17 , Figure 18 , Figure 19 , Figure 20 , Figure 21 , Figure 22 , Figure 23 , Figure 24 and Figure 25 As shown, the mechanized layered assembly construction structure of the prefabricated underground structure includes: bottom foundation layer 10, backfill layer 9, prefabricated components (top opening) 8, prefabricated components (top and bottom double openings) 11, upper prefabricated components 14, The lower prefabricated component 15 and the interlayer connection part 5 .
[0056] The bottom foundation layer 10 is a solid block of cast-in-place concrete, prefabricated concrete, and steel; the bottom foundation layer 10 can be made of various materials and processes, and the appearance geometry of the bottom foundation l...
Embodiment 2
[0060] Embodiment 2: as figure 1 , figure 2 , image 3 , Figure 4 , Figure 5 , Image 6 , Figure 7 , Figure 8 , Figure 9 , Figure 10 , Figure 11 , Figure 12 , Figure 13 , Figure 14 , Figure 15 , Figure 16 , Figure 17 , Figure 18 , Figure 19 , Figure 20 , Figure 21 , Figure 22 , Figure 23 , Figure 24 and Figure 25 As shown, the mechanized layered assembly construction method of the prefabricated underground structure includes the following steps:
[0061] Step 1. Foundation pit excavation and support. The foundation pit support structure adopts a mature support scheme of grading, soil nail wall support, pile (wall) anchor support, and pile (wall) support system.
[0062] Step 2. Apply the bottom base layer. After the foundation pit is excavated to the bottom of the pit, apply the bottom base layer.
[0063] Step 3, if Figure 12 As shown, the first layer of prefabricated components is assembled. After the construction of the bottom...
Embodiment 3
[0069] Embodiment 3: as figure 1 , figure 2 , image 3 , Figure 4 , Figure 5 , Image 6 , Figure 7 , Figure 8 , Figure 9 , Figure 10 , Figure 11 , Figure 12 , Figure 13 , Figure 14 , Figure 15 , Figure 16 , Figure 17 , Figure 18 , Figure 19 , Figure 20 , Figure 21 , Figure 22 , Figure 23 , Figure 24 and Figure 25 As shown, the mechanized layered assembly construction structure of the prefabricated underground structure, the top layer of the foundation is the base layer, and there are enclosure structures on both sides of the foundation. Section trapezoidal or cross-sectional trapezoidal layer; the lower member is placed above the cushion layer, and the trapezoidal opening of the cushion layer has a backfill layer between the side of the lower member and the enclosure structure. The assembly device can raise or lower the upper member, through prestressing Rebars and steel bars are used to connect the upper and lower members. The steel ...