Unlock instant, AI-driven research and patent intelligence for your innovation.

Photovoltaic power station active power distribution method and device based on average price station priority

A photovoltaic power station and active power technology, which is applied in photovoltaic power generation, electrical components, single-network parallel feeding arrangements, etc., can solve problems such as inaccurate active power distribution, achieve the effect of improving market competitiveness and speeding up the process of grid parity

Pending Publication Date: 2021-06-11
ELECTRIC POWER SCI RES INST OF STATE GRID XINJIANG ELECTRIC POWER +1
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The present invention provides a photovoltaic power station active power distribution method and device based on the priority of the parity station, which overcomes the above-mentioned deficiencies in the prior art, and can effectively solve the problem of not considering each photovoltaic power station in the process of active power adjustment of the existing photovoltaic power station Differences in electricity prices lead to inaccurate distribution of active power

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Photovoltaic power station active power distribution method and device based on average price station priority
  • Photovoltaic power station active power distribution method and device based on average price station priority
  • Photovoltaic power station active power distribution method and device based on average price station priority

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0034] Embodiment 1: as attached figure 1 As shown, this embodiment discloses a photovoltaic power station active power distribution method based on the priority of the parity station, including:

[0035] Step S101, obtain the power dispatch command issued by the grid dispatcher, and determine whether it is greater than the total actual power of the photovoltaic field group;

[0036] Step S102, in response to that, according to the principle of preferential power generation of the parity station, the power scheduling command is assigned to the AGC module of each photovoltaic power station, and the AGC execution assignment result of the photovoltaic power station is issued to each photovoltaic power station;

[0037] Step S103, if the response is no, then according to the principle of priority power reduction for non-parity power stations, the power scheduling command is distributed to the AGC modules of each photovoltaic power station, and the AGC execution assignment results ...

Embodiment 2

[0039] Embodiment 2: as attached figure 2 As shown, this embodiment discloses a photovoltaic power station active power distribution method based on the priority of the parity station, including:

[0040] Step S201, obtain the power dispatch command issued by the grid dispatcher, and determine whether it is greater than the total actual power of the photovoltaic field group;

[0041] Step S202, in response to this, determine the pre-allocated value of the parity station, where the pre-allocated value is the sum of the power generation demand and the original power generated by the photovoltaic power station;

[0042] Step S203, select a parity station, and judge whether the pre-allocated value is greater than the power generation limit of the parity station;

[0043] Step S204, in response to this, determine whether the power generation demand exceeds the sum of the power generation margins of the parity stations;

[0044] Step S205, in response to this, adjust the generati...

Embodiment 3

[0048] Embodiment 3: as attached image 3 As shown, this embodiment discloses a photovoltaic power station active power distribution method based on the priority of the parity station, including:

[0049] Step S301, obtain the power dispatch command issued by the grid dispatcher, and determine whether it is greater than the total actual power of the photovoltaic field group;

[0050] Step S302, in response to that, according to the principle of preferential power generation of the parity station, the power scheduling command is assigned to the AGC module of each photovoltaic power station, and the AGC execution assignment result of the photovoltaic station is issued to each photovoltaic station;

[0051] Step S303, judging whether the curtailed power is greater than the sum of the actual power of non-parity stations;

[0052] Step S304, in response to this, set the power of the non-parity station to the lower limit, and allocate the remaining power-limiting tasks to the parit...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of photovoltaic power station control, in particular to a photovoltaic power station active power distribution method and device based on average price station priority. The method comprises the steps of: acquiring a power dispatching command issued by power grid dispatching, and judging whether the power dispatching command is greater than the total actual power of a photovoltaic field group or not; if so, distributing the power dispatching command to an AGC module of each photovoltaic power station according to the principle of preferential power generation of an average price station; and if not, allocating the power scheduling command to the AGC module of each photovoltaic power station according to the principle of preferential power limitation of a non-average-price station. According to the method, the power dispatching command is compared with the total actual power of the photovoltaic field group, whether the power dispatching command corresponds to the power generation task or the power limiting task is judged, and when the power generation task is the power generation task, the power generation requirement of the average-price field station is met preferentially, so that the market competitiveness of the photovoltaic power generation industry in China is improved, the same-price competition with traditional fossil energy power generation is realized early, and the non-subsidy average-price internet surfing process is accelerated.

Description

technical field [0001] The invention relates to the technical field of photovoltaic power station control, and relates to a photovoltaic power station active power distribution method and device based on the priority of parity stations. Background technique [0002] Due to the impact of new energy grid-connected policies, and the different construction locations, scales and periods of power generation plants, the grid-connected electricity price of each photovoltaic power plant varies greatly. At present, dispatching only adjusts the total active power issued by the central control terminal, and then the active power distribution module performs secondary distribution, and sends the distribution results to each power station to execute the distribution results through the station AGC control power algorithm module. This allocation process does not take into account the factors of differences in the electricity prices of various photovoltaic power plants, so the active power ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): H02J3/46
CPCH02J3/46H02J2300/24Y02E10/56
Inventor 刁元鹏杨琪张斌翟保豫马涛魏伟史亚娟董雪涛李星陈冠初阿力马斯别克·沙肯别克段玉
Owner ELECTRIC POWER SCI RES INST OF STATE GRID XINJIANG ELECTRIC POWER