Shield tunneling machine underground diaphragm wall penetrating construction device and construction method thereof
A technology of construction device and ground connection wall, which is applied in earth-moving drilling, mining equipment, tunnels, etc., can solve the problems of inconvenient simultaneous expansion and breaking, and achieve the effect of improving convenience and output efficiency, and improving construction convenience.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0036] see Figure 1-7 , a construction device for shield tunneling under the ground and connected to the wall, comprising a propulsion distance adjustment structure 1, a hole expansion derivation structure 2 and a dynamic guide reaming structure 3, the top of the propulsion distance adjustment structure 1 is fixedly connected with a four-way synchronous expansion output One of the four ends of the reaming derivation structure 2 is provided with a dynamic guide reaming structure 3, and the dynamic guide reaming structure 3 is used for crushing soil.
[0037] The propulsion distance adjustment structure 1 includes a matching inner block 4, a first motor 5, a screw rod 6, a polished rod 7 and a matching pushing block 8, and one end of the matching inner block 4 is fixedly connected with a first motor 5, and the first motor 5 The output end of the screw rod 6 is fixedly connected with the screw rod 6, and the end of the screw rod 6 away from the first motor 5 is rotationally conn...
Embodiment 2
[0048] A construction method of a shield machine passing through the ground and wall construction device, which is applicable to the above-mentioned embodiments:
[0049] Step 1: Mount the device as a whole at the location where openings need to be expanded in a small local area;
[0050] The second step: by controlling the advancing distance adjustment structure 1, the derivation of the output distance of the reaming derivation structure 2 and the dynamic guide reaming structure 3 is completed, so that the dynamic guide reaming structure 3 is inserted into the interior of the soil;
[0051] The 3rd step: start moving guide reaming structure 3 to complete rotation;
[0052] The fourth step: start the reaming derivation structure 2 to complete the automatic derivation and drive of the position adjustment of the four ends, and complete the expansion.
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 