A technology of earth pressure balance shield tunneling and correction method, which is applied in the fields of prediction, instrumentation, and data processing applications, and can solve problems such as large deviation, low precision of slag discharge prediction value, popularization and application, and excessive surface displacement
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0046] The present invention will be further described below in conjunction with the accompanying drawings. It should be noted that this embodiment is based on the technical solution, and provides detailed implementation and specific operation process, but the protection scope of the present invention is not limited to the present invention. Example.
[0047] figure 1 It is a flowchart of a method for estimating and correcting the slag output of an earth pressure balance shield tunneling machine according to an embodiment of the present invention, as shown in figure 1 Shown, the present invention comprises the following steps:
[0048] S1. Cleaning the earth pressure balance shield tunneling parameter data;
[0049] Preferably, step S1 specifically includes the following steps:
[0050] S11, export the tunneling parameter data of the previous n rings, and number the tunneling parameters of the shield tunneling machine, and the tunneling parameters of the shield tunneling se...