Shield driving and synchronous road construction method for double layer highway tunnel
A technology for simultaneous construction of road tunnels, applied in roads, tunnels, roads, etc., can solve problems such as no simultaneous construction method for double-layer road tunnels, and achieve the effect of shortening the construction period and speeding up the construction process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] Use the 20T ground crane 9 to transport the construction segments and road slabs 17 from the ground to the tunnel through the working shaft 7, and multiple 14T electric locomotives 6 in the tunnel drive the segment flat car 5 to transport the segments and drag the shield The special takeover trolley 4 for construction transports the ring-forming segment 11 for the excavation and laying of the shield machine 1,
[0026] When the shield is excavated, the ring segment 11 protruding from the inner side of the ring to protrude the support bump 25 is installed, and the road slab 17 that divides the upper and lower layers is laid on the support bump 25 synchronously; at the negative ring segment of the working well 7, A wellhead steel platform 28 with an opening 21 is set, which is used as a vertical passage entrance for transporting workpieces from the ground to the lower layer of the tunnel from the wellhead, forming separate transportation passages and construction sites for...