Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Synchronous construction method of open hard rock roadheader and secondary lining

A technology of hard rock roadheader and secondary lining, applied in wellbore lining, tunnel lining, earthwork drilling, etc., can solve the problems of tight construction period, harsh natural conditions, long distance of raw material transportation, etc., to relieve construction period pressure and completion time. early effect

Active Publication Date: 2011-12-07
CHINA RAILWAY TUNNEL GROUP CO LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0008] For long-distance traffic tunnels, open-type hard rock roadheaders are mostly used. Due to the mutual interference and influence of the two lining constructions at the same time as the TBM tunneling construction, especially the mutual interference and influence on transportation and construction organization issues , the existing technology can only perform secondary lining on the tunnel surrounding rock after the tunnel excavation is completed and the TBM is removed, which often requires a long construction period
Therefore, there are various unfavorable factors such as tight construction period, difficult construction, harsh natural conditions, and long distances for transportation of various raw materials.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0012] Example 1: Simultaneously with the TBM excavation, the secondary lining of the tunnel is carried out synchronously. The implementation method is to start the secondary lining construction when the TBM excavation is about 1000m long, and use three sets of transport trains to marshal the TBM excavation within the length of 0-6km, and then add 3km for each additional 3km. For one formation, 5 trains are used at most, and one train is used as a backup; two 16.5m formwork trolleys are used for the secondary lining, and the distance between the two trolleys is about 500m. Waterproof board laying platform and repair frame; second lining concrete pouring prepares two marshalling cars for supplying concrete, and prepares another motorized train, a total of five trains.

[0013] Secondary lining power consumption plan: Install a "T" joint every 800m on the 10,000-volt main cable entering the hole, and install a cable reel on the lining repair trolley to ensure that the power suppl...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The simultaneous construction method of open hard rock roadheader excavation and secondary lining involves the construction method of open type hard rock roadheader construction excavation and secondary lining process synchronous follow-up and connection. While TBM excavation is carried out, the tunnel secondary lining is carried out synchronously. The implementation method is to start the secondary lining construction when the TBM excavation is about 1000m. The secondary lining is equipped with its own waterproof board laying platform and repair frame; Efforts should be made to solve the mutual interference and influence between the secondary lining construction and the TBM tunneling construction, especially the mutual interference and influence on the transportation and construction organization issues, so as to ensure the smooth and rapid secondary lining construction simultaneously with the TBM tunneling , Simultaneously, relieve the pressure of the project schedule, and the completion time is significantly ahead of schedule.

Description

Technical field: [0001] The invention relates to a construction method in which the excavation of an open-type hard rock roadheader is simultaneously followed up and connected with the secondary lining process, in particular to the simultaneous construction method of the open-type hard-rock roadheader and the secondary lining. Background technique: [0002] When the length of the tunnel and the hole is too long, it will take a long time to construct the tunnel with the conventional drilling and blasting method, and the tunnel boring machine method is more suitable for the construction of long tunnels. The English name of the tunnel boring machine is Tunnel Boring Machine, or TBM for short. TBM is highly targeted, and different geological conditions require different roadheaders, resulting in different roadheaders; some are suitable for soft soil, also known as shield machines; some are suitable for rocks. Rock boring machines can be divided into open type, single-shield typ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/00E21D11/00
Inventor 谭顺辉魏文杰陈文忠何中文谭小波董天洪鱼建玲张宁川刘二召罗岩松王成鲲崔原周振国刘招伟张洪星王小平石曲张鑫崔文斌赵华杨立新
Owner CHINA RAILWAY TUNNEL GROUP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products