Soil side slope or tailings dam drainage construction method
A soil slope and construction method technology, applied in the field of geotechnical engineering, can solve problems such as low efficiency, large construction distance, complex construction procedures, etc., and achieve the effect of fewer operating procedures, simple construction, and convenient return of drill pipes
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] A seepage drainage construction method for soil slopes or tailings dams, comprising the following steps:
[0020] Step 1 Drilling:
[0021] Fix the directional drilling machine 2 at a designated position on the tailings dam 1, and drill holes from bottom to top according to the design requirements until the design position is reached. If drilling from top to bottom is adopted, the sand stop ring may not be used when withdrawing the drill pipe .
[0022] Step 2 Install the drainage pipe:
[0023] When the hole is drilled to the designed position, the directional drilling machine 2 bit or the connecting rod of the drilling rig power head are removed, and the drill pipe 3 is directly used as the construction sleeve of the seepage pipe, and the prefabricated seepage pipe 4 is placed in the drill pipe 3 . The seepage pipe 4 is a known technology. Use PE pipe or PPR water supply pipe. The drainage holes on the pipe are arranged in a plum blossom shape. The drainage pipe 4 ...