Controlled blasting construction method for shallow-buried large-section tunnel
A technology for controlling blasting and construction methods, applied in blasting and other directions, can solve problems such as slow progress, excessive blasting vibration, and unreliable results, and achieve the effects of speeding up construction progress, improving social benefits, and reducing process time.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] The present invention will be further described below in conjunction with the accompanying drawings.
[0029] A kind of shallow-buried large-section tunnel control blasting construction method described in the present invention, such as figure 1 shown, including the following steps:
[0030] 1. Construction preparation
[0031] It is mainly the processing of simple drilling trolley. According to the tunnel excavation section size and construction habits, the full-section simple drilling jumbo is processed on site. It is required to install high-pressure air pipes and high-pressure water pipes on the trolley so that they can be directly connected to the air gun through gate valves and connecting hoses; the trolley is equipped with equipment such as power distribution boxes and lighting fixtures for convenient use during construction.
[0032] 2. Detonation test
[0033] The ultimate purpose of the blasting test is to determine the maximum charge per delay detonator i...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com