Beam-slab framework early removal construction method

A construction method and formwork technology, applied in formwork/formwork/work frame, formwork treatment, construction material treatment, etc., can solve the problem that the stress state is not as good as the slab-assisted floor, the floor slab is demolished early, and the application scope is narrow, etc. question

Inactive Publication Date: 2011-07-13
李万山 +2
View PDF4 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This technology uses an early demolition device to directly support the bottom formwork of the top plate, so that the span of the formwork demolition structure becomes less than 2M. When the concrete strength reaches 10MPa or more, the early demolition of the formwork can be implemented; its existing problems and deficiencies: ① only solve the problem below 2m The problem of early demolition of the span floor is narrow in scope of application; ②The variable-span early demolition device needs to be processed by professional manufacturers, which is inconvenient for construction; The state is not as good as the board to help the floor

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Beam-slab framework early removal construction method
  • Beam-slab framework early removal construction method
  • Beam-slab framework early removal construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0117] [Example]: A building with a 7-story frame structure, a room with a bay of 4.2×6m, a roof thickness h=100mm, roof reinforcement ∮8@150, and a concrete design strength of C25. Early demolition of the formwork is carried out. The specific implementation methods are as follows:

[0118] 1. Perform cross-change processing

[0119] A 10CM*10CM wooden square is set in the short direction at the middle of the bottom of the 6m span of the floor as the sub-keel, and 4 vertical poles are set at the bottom of the sub-keel as supports, and the distance between the poles is 1400mm. Make the 4.2×6m two-way slab into a 3×4.2m two-way slab formwork removal structure.

[0120] 2. Determine and calculate the early demolition strength and early demolition time

[0121] The structural parameters of the 3×4.2m span floor, span L=3m, plate thickness h=100mm, reinforcement As=335mm 2 , compared with the attached table 1 of the early demolition construction application manual of the formwork...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a beam-slab framework early removal construction method. The method comprises the following steps: (1) span changing treatment is performed, wherein a technical measure of adding a single row of upright poles under a secondary joist of 10*10cm square lumber at the bottom of a longitudinal mid-span part of a slab for supporting is adopted, the square lumber secondary joist separates the slab with the span more than 4m into a bidirectional plate structure with the early removal span between 2 and 4m in a beam support mode; and in the same way, the technical measure that double poles are vertically added at the bottom of the beam every other 2.6 to 4m for a supporting is adopted, and the beam is turned into a framework removal structure with the early removal span between 2.6 and 4m; (2) the structure strength, rigidity and crack width in framework early removal are determined and calculated according an existing formula, and when the calculation results meet requirements at the same time, early removal construction is permitted; and (3) framework early removal construction is performed, wherein after the lowest permitted framework removal strength is determined, the actual early removal strength of concrete is calculated on the basis of the pressure testing strength of a test block is maintained under the same condition; whether the actual early removal strength is more than the calculated early removal strength or not is judged, and if the actual early removal strength is more than the calculated early removal strength, a later removal support system can be maintained, and other framework supports are removed.

Description

1. Technical field [0001] The invention relates to a construction method in the construction field, in particular to a construction method for early demolition of beam-slab formwork. 2. Background technology [0002] The Beijing local standard "Technical Regulations for Formwork Early Demolition Construction" No. DB11 / 694-2009, will come into effect on July 1, 2010. This technology uses an early demolition device to directly support the bottom formwork of the roof, so that the span of the formwork removal structure becomes less than 2M. When the concrete strength reaches 10MPa or more, the formwork can be demolished early; its existing problems and deficiencies: ① Only solve the problem below 2m The problem of early demolition of the span floor is narrow in scope of application; ②The variable-span early demolition device needs to be processed by a professional manufacturer, which is inconvenient for construction; The state is not as good as that of Banzhulou. [0003] "Res...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/00E04G19/00E04G11/36E04G13/04
Inventor 李万山李维李戌戴连双
Owner 李万山
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products