[0016] Such as figure 1 with figure 2 As shown, the present invention provides a fast and safe masonry support method in an over-elevation area, and the support method includes the following steps:
[0017] Step 1. In the roadway 9 that has been supported, fix five waste and old channel steels or I-beams 1 on the roadway wall, and the five channel steels or I-beams 1 protrude out of the supported roadway 600mm~1000mm (the distance can be determined according to the step distance of the masonry);
[0018] Step 2: Construction personnel stand under the supported roadway 9, place the reinforcement mesh or lead wire mesh 2 on the outside of the five channel steels or I-beams, and overlap the outer mesh of the roadway with the built-in wall by 100mm ( 100mm is reserved for overlapping with the next cycle when the last cycle is laid, and the lap section 7 is fastened with No. 8 lead wire every 100-200mm;
[0019] Step 3. Under the protection of the five channel steels or I-beams...
PUM
Login to View More Abstract