A construction method and construction planning technology, applied in the processing of building materials, construction, building maintenance, etc., can solve the problems of long construction period, long construction time and cost of substructure reinforcement, so as to improve construction speed, ensure construction quality and safety. , the effect of reducing manufacturing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0018] The present invention will be further described in conjunction with the accompanying drawings.
[0019] Figure 4 It is the layout plan of the conversion beam for the measure, which shows that the lower shear wall cannot be constructed due to the unfinished reinforcement, and the upper structural shear wall can transfer the load of the upper shear wall to the column through the beam of this measure.
[0020] Such as figure 1 , figure 2 , image 3 Shown, specific embodiment of the present invention carries out according to the following steps:
[0021] (1) First remove part of the beams and slabs of the original structure 1 to make it suitable for upward construction, conduct a comprehensive inspection of the wall columns 3 and beams and slabs 4 of the original structure 1, and evaluate the status of the structure itself, according to the original structure design drawings Determine the mechanical performance of the wall column 3 of the original structure based on t...
PUM
Login to View More Abstract
Description
Claims