[0020] Such as Figure 1 to Figure 3 As shown, the silt-filled vacuum pre-compression embankment construction method of the mold bag of this embodiment includes the following steps:
[0021] Step 1. After leveling the target beach, lay at least one layer of sealing film to seal the bottom;
[0022] The second step is to lay a layer of filling mold bag 1 with a filling port on the sealing film, and then use a pump to fill the sludge from the filling port 2 into the mold bag 1;
[0023] The third step is to insert one side of a set of drainage plates 3 into the side of the mold bag 1 transversely, and leave the drainage plate 3 outside the mold bag 1 and tie the corresponding permeable pipe 4 to the other side; then use the one with an external nozzle The pipeline is connected to all permeable pipes 4;
[0024] The fourth step is to lay at least one layer of sealing film 5 on this layer of the mold bag 1, and press the edge of the sealing film 5 into the sealing groove preset around th...