Wind power bundling control method after wind power and thermal power accessing to power grid
一种控制方法、接入电网的技术,应用在风能发电、电气元件、电路装置等方向,能够解决风火协调优化控制缺乏研究等问题,达到确保合理出力、保障正常运行的效果
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0023] figure 1 It is a flowchart of a wind power bundling control method after wind power and thermal power are connected to a power grid. Such as figure 1 As shown, the wind power bundling control method proposed by the present invention after wind power and thermal power are connected to the grid includes:
[0024] Step 1: Adjust the output of wind power and thermal power positively, or reversely adjust the output of wind power and thermal power. The positive adjustment of the output of wind power and thermal power is specifically to reduce the output of thermal power and increase the output of wind power. Reversely adjust the output of wind power and thermal power specifically to reduce the output of wind power and increase the output of thermal power.
[0025] Step 2: Calculate the transient stability margin λ of the power grid after adjusting the output of wind power and thermal power respectively Sl , component load index λ L and bus voltage limit index λ U .
[...
Embodiment 2
[0042] The content of the present invention will be further described below by taking the power grid in the Hexi region of Gansu in 2012 as an embodiment of the present invention.
[0043] Wiring diagram of power grid in Hexi area, Gansu figure 2 shown. In 2012, the total installed capacity of wind power in Gansu grid was 6,915.1 MW, and the total installed capacity of thermal power was 4,500 MW. Gansu's wind power output plan in October 2012 is 2800MW, which is the maximum value of wind power output.
[0044] It is determined that the key sections of Gansu Hexi Power Grid are the 750kV Dunhuang-Jiuquan double-circuit line section, the 750kV Jiuquan-Hexi double-circuit line section and the 750kV Hexi-Wusheng double-circuit line section. 1.
[0045] key section
Transient stability limit (MW)
Section of 750kV Dunhuang-Jiuquan Double Circuit Line
3400
Section of 750kV Jiuquan-Hexi double circuit line
3400
Section of 750kV Hexi-Wusheng...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com