A construction method of Beijing brick decorative wall

A construction method and technology for decorating walls, applied to walls, building components, coverings/linings, etc., can solve problems such as difficulty in precision control, and achieve the effect of ensuring construction precision, simple construction, and simple wall appearance

Active Publication Date: 2016-01-06
JUJIANG CONSTR GRP
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0008] The above two patents are related to the decoration of flat walls, but for walls with slopes and arcs, it is very difficult to control the accuracy during construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method of Beijing brick decorative wall
  • A construction method of Beijing brick decorative wall

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] The specific implementation manner of the present invention will be described in detail below in conjunction with the accompanying drawings.

[0031] Such as figure 1 A Beijing brick decorative wall is shown. The outer surface of the decorative wall is an inclined arc surface. The wall of the decorative wall includes a main wall 1, a concrete pouring layer 2 and a Beijing brick decorative layer 3 from the inside to the outside. The outer surface of the main wall 1 is also an inclined arc, and the outer surface of the main wall 1 is laid with a reinforcement mesh 4; Both ends are fixedly arranged on the main wall body 1 , and the grid passing through the steel mesh 4 in the middle fixes the said steel mesh 4 on the main wall body 1 . Described Beijing brick decorative layer 3 is formed by building by laying bricks or stones 6 along the outer surface of main body of wall 1, and the upper surface of described every piece of Beijing brick 6 is provided with pulling hole 7,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the field of buildings, in particular to a construction method of a Beijing brick decorating wall. The decorating wall comprises a main wall body, a concrete pouring layer and a Beijing brick decorating layer sequentially from inside to outside. The outer surface of the main wall body is an inclined cambered surface and is provided with a steel mesh. The construction method includes 1, drilling a pulling hole in each Beijing brick; 2, manufacturing a steel hook; 3, processing the base layer of the main wall body; 4, bonding the steel mesh, and pulling lines for positioning; 5, arraying and laying the bricks, arranging the steel mesh to fix the Beijing bricks, and pouring masonry mortar; 6, pouring the concrete pouring layer, arranging ring beams, and pointing and wiping seams. According to the technical scheme, the combining strength of the Beijing bricks and the wall body is improved, and constructing accuracy of the inclined and cambered wall body are guaranteed; the construction method has the advantages that construction is facilitated, and the appearance of the wall body are primitively simple and attractive.

Description

technical field [0001] The invention relates to the field of construction, in particular to a construction method for a decorative wall. Background technique [0002] Jiashan Beijing Bricks, also known as "Golden Bricks", began in the Song Dynasty and flourished in the Ming and Qing Dynasties. The production of Beijing bricks has to go through multiple processes such as soil extraction, billet making, firing, kiln exit, grinding and soaking, and seven processes of excavation, transportation, drying, vertebral, pulping, grinding, and sieving, which take up to 8 hours. months. [0003] Jiashan Jing brick is an ancient building material, mainly used for ground laying. Its shape is square, commonly known as square bricks. Its quality is fine and dense, and its color is Qingdai. The best Beijing bricks are as hard as stone after unique production. Such as laying the ground, stepping on it for a long time, grinding like a mirror for a long time, shining like black gold, also ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04B2/00E04F13/073E04F13/21E04F13/22E04F13/14
Inventor 曹应标沈建良沈伟明陈烨蔡会平