Effective method for solving multi-target resource-constrained project scheduling

A resource-constrained, multi-objective technology, applied in the field of solving multi-objective resource-constrained project scheduling, can solve problems such as difficulty in obtaining optimal benefits, difficult adjustment of construction period and cost, etc.

Inactive Publication Date: 2014-12-17
XIAN UNIV OF TECH
View PDF1 Cites 17 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The purpose of the present invention is to provide an effective method for solving multi-objective resource-constrained project scheduling, which solves the problem that the existing scheduling method is difficult to adjust between the construction period and cost in scheduling, and it is difficult to obtain the best benefit

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Effective method for solving multi-target resource-constrained project scheduling
  • Effective method for solving multi-target resource-constrained project scheduling
  • Effective method for solving multi-target resource-constrained project scheduling

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0042] The present invention will be described in detail below in combination with specific embodiments.

[0043] The goal of the resource-constrained project scheduling problem with construction period-cost optimization to be solved by the present invention is to generate feasible scheduling sequences and pattern sequences under the premise of satisfying work sequence constraints and resource constraints, and determine the project duration and corresponding costs. The shortest project duration and the lowest comprehensive cost.

[0044] The effective method of the present invention for solving multi-objective resource-constrained project scheduling is specifically implemented according to the following steps:

[0045] Step 1. Establish a multi-objective resource-constrained project scheduling mathematical model based on duration-cost optimization

[0046] Assuming that the number of jobs in the project is J, and there are timing constraints between each job j, then there are...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an effective method for solving multi-target resource-constrained project scheduling. The method comprises the following steps: (1) establishing a multi-target resource-constrained project scheduling mathematical model based on duration-cost optimization; (2) generating an initial feasible scheduling sequence; (3) evaluating the scheduling sequence; (4) updating the scheduling sequence; (5) configuring non-dominated disaggregation operation; (6) maintaining an external archive set; and (7) performing updating iteration till an optimal solution set is output. According to the method disclosed by the invention, each intelligent body corresponds to a linked list sequence in a scheduling problem, the scheduling sequence of a task linked list and a corresponding execution mode sequence are coded respectively, decoding operation is performed by adopting a serial method, and evolution and update are performed among the linked list sequences through competition, intersection and self-learning; and a project scheduling plan is adjusted, so that comprehensive optimal duration and cost are realized within a control period on the premise of satisfying conditions such as timing constraint and resource constraint.

Description

technical field [0001] The invention belongs to the technical field of system scheduling and control, and relates to an effective method for solving multi-object resource limited project scheduling. Background technique [0002] Resource-constrained project scheduling problem is widely used in scheduling fields such as construction engineering, transportation, software development, product production, power system, etc. The difficulty is to reasonably arrange project tasks according to certain rules under the premise of satisfying timing constraints and resource constraints , and there are multiple modes in the project execution process, which require a trade-off between multiple conflicting goals while optimizing the use of cost resources, find the best balance point between the goals, and get the satisfaction of the project. A set of optimal solution sets required. Therefore, the research on multi-objective resource-constrained project scheduling, which comprehensively co...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06
Inventor 吴亚丽郭晓平薛芬
Owner XIAN UNIV OF TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products