Metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method

A technology of space-time dynamics and construction methods, applied in the field of mining system engineering and mine optimization, can solve the problems of lack of flexibility, real-time and scientific nature

Inactive Publication Date: 2016-09-21
XI'AN UNIVERSITY OF ARCHITECTURE AND TECHNOLOGY
View PDF1 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The managers of mining enterprises are often more accustomed to taking the total ore mining volume of the mine and the reasonable stripping ratio as the assessment objectives of annual production, rather than organizing and implementing production plans based on economic indicators such as the

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method
  • Metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method
  • Metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0045] The implementation of the present invention will be described in detail below in conjunction with the drawings and examples.

[0046] Such as figure 1 As shown, a method for constructing a 5D space-time dynamic production scheduling model of a metal open-pit mine, the specific implementation steps are as follows:

[0047]Step 1: In the field of open-pit mining, divide the ore body and rock mass into three-dimensional discrete mining blocks. The size of the block is divided according to actual needs, usually based on the height of the steps, the size of the open-pit boundary, and the accuracy of simulated mining, etc. According to requirements, for example, most metal open-pit mining steps are usually 12 meters, so the block size in the boundary can be divided by blocks with a length of 10 meters, a width of 10 meters, and a height of 6 meters. After division, each block is The smallest mining unit within the boundary; at the intersection of the open-pit mine boundary a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method which mainly comprises the following steps: building a 3D open-pit mine rock mass block production scheduling model; carrying out space block model attribute assignment; building an ore price and mining and rock mass stripping cost database; and finally, building a 5D temporal-spatial dynamic production scheduling model. The invention aims to realize dynamic simulated mining of a mine rock mass within the open-pit mine boundary. By making use of the 5D temporal-spatial dynamic production scheduling model, the medium- and long-term mining progress and process can be simulated accurately, the obtained resource net value can be calculated dynamically, a mining scheme maximizing the resource net value can be selected for a mine from a variety of medium- and long-term mining schemes, and the discount rate can be further considered to enable mine enterprises to select a medium- and long-term progress plan scheme maximizing the net present value NPV. The metal open-pit mine 5D temporal-spatial dynamic production scheduling plan model building method has a broad application prospect in the field of open-pit mine development optimization design.

Description

technical field [0001] The invention belongs to the technical field of mining system engineering and mine optimization, and in particular relates to a method for constructing a 5D spatiotemporal dynamic production planning model of a metal open-pit mine. Background technique [0002] At present, the medium and long-term production plans of most metal open-pit mines in my country (usually more than 5 years are called medium and long-term) production plans often have the phenomenon of "one-time preparation and long-term use", and only pay attention to medium and long-term progress planning at a certain static time point. During the preparation of the plan, mining parameters such as production scale, ore grade ore blending, and stripping ratio are mainly considered. However, the market environment is affected by various random factors and there are many uncertainties. Mining companies often ignore ore market prices and For changes in economic parameters such as production costs, ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q50/02G06F17/50G06T17/10G06Q30/02G06F17/30
CPCG06F16/90G06Q30/0206G06Q30/0283G06Q50/02G06T17/10G06F30/367
Inventor 顾清华卢才武张雯聂兴信杨震郭梨
Owner XI'AN UNIVERSITY OF ARCHITECTURE AND TECHNOLOGY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products