A Deck Crane Method for Composite Girder Cable-Stayed Bridges in Mountainous Areas
A machine method and technology in mountainous areas, which is applied in the field of deck crane method of superimposed beam cable-stayed bridges in mountainous areas, can solve the problems of narrow site, large amount of construction work and high cost of the main tower attachment, and achieve reduced construction costs and high construction quality. , the effect of small engineering
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The present invention will be further described below in conjunction with the accompanying drawings and embodiments, but not as a basis for limiting the present invention.
[0025] A deck crane method for a composite beam cable-stayed bridge in mountainous areas, which consists of the following steps: Figure 1-6 shown, including the following steps:
[0026] (a) Install steel main beam 0﹟section 31;
[0027] (b) A plurality of steel main beams 3 are assembled with steel main beam parts 5 at the position of the side span platform; the side span platform is an assembly platform where steel main beam parts 5 are arranged at the side span position;
[0028] (c) Starting from the 0﹟ section 31 of the steel main beam from the side span, hoist, transport, install the steel main beam (3) 1--N﹟ section on the side span side and the middle span side in turn, and install the stay cables in sequence 6, where N≥2;
[0029] (d) Set up bridge deck steel girder prefab 1 on the segm...