A PDA-based daily work planning method for on-site operation and maintenance

An operation and maintenance and planning technology, applied in the field of dispatching, can solve the problems of waste of operation and maintenance resources, low efficiency, lack of accurate dispatching algorithms, etc., to achieve the effect of optimizing capacity, realizing workload, and solving urgency optimization.

Active Publication Date: 2020-11-03
STATE GRID ZHEJIANG ELECTRIC POWER +2
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] Due to the lack of accurate dispatching algorithms, in this case, we have to wait for the operation and maintenance personnel to come back and dispatch workers again, which leads to low efficiency and waste of operation and maintenance resources.
Either directly dispatch workers, which will easily lead to the inability to accurately arrange the follow-up work route of the operation and maintenance personnel. Only the personal experience of the operation and maintenance personnel can only be used.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A PDA-based daily work planning method for on-site operation and maintenance
  • A PDA-based daily work planning method for on-site operation and maintenance
  • A PDA-based daily work planning method for on-site operation and maintenance

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0069] The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings.

[0070] like figure 1 Shown, the present invention comprises the following steps:

[0071] 1) Obtain abnormal point aggregation to generate abnormal work orders;

[0072] 2) Filter abnormal work orders according to the dispatch area;

[0073] 3) Calculate the shortest path from the maintenance point to the stagnation point and the mutual shortest path of the abnormal work order;

[0074] 4) Generate a repeating path matrix according to the shortest path from the maintenance point to the stagnation point and the mutual shortest path;

[0075] 5) generate a preliminary route list by scanning the repeated route matrix, and obtain the preliminary dispatch route;

[0076] 6) Preliminary routes are sorted in descending order of urgency;

[0077] 7) Select the preliminary route with the greatest urgency, and judge whether to add or dele...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a PDA based onsite maintenance day work planning method, belongs to a dispatching method, and aims at solving the problems that the prior art lacks an accurate dispatching algorithm, the efficiency is low and maintenance resources are wasted. The method comprises the following steps that abnormal points are combined to generate an abnormal work order; the abnormal work order is filtered according to a dispatching area; a shortest path from a maintenance point of the abnormal work order and an arrest point and a mutual shortest path are calculated; a repeated path matrix is generated; the repeated path matrix is scanned to generate an initial route list, and preliminary dispatching routes are obtained; the preliminary dispatching routes are ordered in the descending order of emergency degrees; the preliminary route of the highest emergency degree is selected, and whether points are added to or deleted from the selected preliminary route is determined; and a point adding or deleting algorithm is executed to generate a fine dispatching route, so that the workload of each dispatching route is saturated but not exceed a prescribed workload and the total emergency degree of the route is high. An accurate dispatching algorithm is realized, a maintenance staff can be directly to another place onsite needless of coming back, the efficiency is high, and waste of maintenance resources is low.

Description

technical field [0001] The invention relates to a dispatching method, in particular to a PDA-based on-site operation and maintenance daily work planning method. Background technique [0002] In the current operation and maintenance of power collection systems across the country, either PDAs have not yet been used for on-site office work, or PDAs are only used as on-site work records and certain links in the work order process. There is no system that can guide and arrange on-site work after O&M emergencies. [0003] Because when the operation and maintenance personnel are in the dispatched state, there are often emergencies that need to be temporarily added to the dispatched work. For example, in the area where the operation and maintenance personnel are dispatched, it is necessary to ensure that the user has a collection exception. Or for remote areas such as Tibet / Xinjiang, where one operation and maintenance takes several days, abnormal collection occurs suddenly in the...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): G06Q10/04G06Q10/06G06Q10/00G06Q50/06
CPCG06Q10/047G06Q10/06311G06Q10/06316G06Q10/20G06Q50/06
Inventor 张燕应鸿裘华东郑斌李熊王伟峰严华江董伟
Owner STATE GRID ZHEJIANG ELECTRIC POWER
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products