Construction method of pulling knots between external scaffolding and internal wall connectors
A technology of inner connecting piece and outer scaffolding, which is applied in the accessories of scaffolding, scaffolding supported by house structure, support of house structure, etc., to achieve the effect of preventing leakage, easy disassembly and assembly, and obvious advantages.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] Such as figure 1 and figure 2 Shown, the tie construction method of external scaffolding of the present invention and connector in the wall, comprises the following steps:
[0030] (1) Process and manufacture the connecting parts inside the wall;
[0031] (2) Drill installation holes at selected positions on the inner aluminum formwork 1 and outer aluminum formwork 2 arranged in parallel, and install and fix the connectors in the wall in the corresponding installation holes between the inner aluminum formwork 1 and the outer aluminum formwork 2 reliable;
[0032] (3) Concrete mortar is poured between the inner aluminum formwork 1 and the outer aluminum formwork 2;
[0033] (4), after the concrete mortar is solidified to form the wall 13, remove the reusable components of the connectors in the wall, and then remove the inner aluminum formwork 1 and the outer aluminum formwork 2;
[0034] (5) Use the connecting bolt 14 to extend into and thread into the connector ins...