A supportless construction method for a ring cable-supported grid structure
A technology of grid structure and construction method, applied in special structures, building components, building structures, etc., can solve problems such as unfavorable stand protection, unfavorable cable installation, and large number of radial cable roots, and achieves favorable stand protection. , The effect of reducing construction risks and saving construction costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] Taking the annular cable-bearing grid canopy structure project of a stadium I as an example, the upper grid 5 of the structure is a cross-type, with a total of 36 radial cables 6, and each radial cable 6 has three support rods, which are The inner strut 8, the middle strut 9 and the outer strut 10, wherein the inner strut 8 is directly connected with the hoop cable 7 figure 2 . According to the characteristics of the project and the hoisting capacity, the upper cross grid is divided into unit Ia11, unit Ib12, unit Ic13, unit Id14 and unit Ie15. For the specific hoisting unit division, see image 3 .
[0047] The specific construction steps are as follows:
[0048] Step 1: Install the column 2, the outer ring beam 3 and the outer grid 4; spread the radial cable 6 and the hoop cable 7 on the stand 1 and connect them in a network, see Figure 4 ;
[0049] The second step: lift the cable net by pulling the outer end of the radial cable 6 obliquely by the pulling device...
Embodiment 2
[0059] Take the annular cable-bearing grid canopy structure project of a stadium II as an example. The upper grid 5 of the structure is of a rib ring type, with a total of 72 radial cables 6, and each radial cable 6 has 3 struts, which are the inner strut 8, the middle strut 9 and the outer strut 10, respectively. The inner strut 8 is directly connected with the hoop cable 7 Figure 14 . According to the project characteristics and hoisting capacity, the upper grid 5 is divided into unit IIa16, unit IIb17 and unit IIc18, the same as above. For the specific hoisting unit division, see Figure 15 .
[0060] The specific construction steps are as follows:
[0061] Step 1: Install the column 2 and the outer ring beam 3; spread the radial cable 6 and the ring cable 7 on the stand 1 and connect them in a network, see Figure 16 ;
[0062] The second step: lift the cable net by pulling the outer end of the radial cable 6 obliquely by the pulling device 19, connect the outer end ...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


