Fabricated cap beam mould and construction process
A prefabricated and beam-covering technology, which is applied in the direction of erecting/assembling bridges, mold auxiliary parts, bridges, etc., can solve problems affecting work progress, stoppages, untimely scheduling of truss trucks, etc., to reduce workload, avoid seams, The effect of improving productivity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0042] Below we will further elaborate on the assembled cap beam mold of the present invention and the construction process during use in conjunction with the accompanying drawings and specific embodiments, in order to understand its structural composition and working mode more clearly, but it cannot be based on this To limit the protection scope of the present invention.
[0043] Such as Figure 1-13 As shown, the assembled cover beam mold of this embodiment includes a bottom mold 1, two side molds 2 and two end molds 3,
[0044] The bottom mold 1 includes two bending end portions 11 and a middle section horizontal steel mold 12, and the outer sides of the two bending end sections 11 are provided with a support frame 13, and a sleeve is arranged on the middle section horizontal steel mold 12. cylinder positioning plate 14,
[0045] The side form 2 includes a vertical bar 21 and a cross bar 22, the vertical bar 21 and the cross bar 22 form a side form support, the upper end ...