[0099] Attached below Figure 1~4 The present invention is further described:
[0100] Such as figure 1 , 2 , 3, shown in 4, on the underground garage roof of the present invention, lift bearing capacity check and construction method are installed, it is characterized in that take the following steps:
[0101] 1. Determine the model and installation height of the lift 15
[0102] Determine the type and installation height of the elevator 15 according to the vertical transportation workload of the construction project and the height of the building;
[0103] 2. Lift foundation 3 drawing positioning
[0104] On the roof structure diagram of the underground garage, select the position of the window opening 2 where the inner edge of the elevator foundation 3 is 0.6m to 1.5m away from the outer edge of the main building exterior wall 1 to draw the floor plan of the elevator foundation 3;
[0105] 3. Calculation of Design Value of Uniformly Distributed Live Load of Lift Foundat...