Optimized construction method for double-arc tunnel
A construction method and technology for multi-arch tunnels, which are applied to tunnels, tunnel linings, and earth-moving drilling and mining, etc., can solve problems such as hidden quality problems of top poured concrete voids, difficulty in installing and removing formwork, slow construction progress, etc. The effect of fast speed and reduced process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0058] Such as Figure 1-5 Shown, a kind of multi-arch tunnel optimization construction method of the present invention comprises the following steps:
[0059] (1) Temporary support after the pilot tunnel 1 in mechanical excavation by step method;
[0060] (2) Install a profiled steel arch frame on the side of the middle pilot tunnel 1 near the first hole 2, and then carry out the construction of hanging nets, connecting bars, anchor rods and sprayed concrete, and form the primary support structure by installing profiled steel arch frames, hanging nets and sprayed concrete construction 4;
[0061] (3) Plain concrete 5 is integrally backfilled on the side of the middle pilot tunnel 1 near the rear tunnel 3;
[0062] (4) The first hole 1 is mechanically excavated by the step method, and the initial support is closed to form a ring;
[0063] (5) The rear tunnel 3 is mechanically excavated by the step method, and the initial support is closed to form a ring.
[0064] Wherein, ...
Embodiment 2
[0071] Such as Figure 1-5 Shown, a kind of multi-arch tunnel optimization construction method of the present invention comprises the following steps:
[0072] (1) Temporary support after the pilot tunnel 1 in mechanical excavation by step method;
[0073] (2) Install a profiled steel arch frame on the side of the middle pilot tunnel 1 near the first hole 2, and then carry out the construction of hanging nets, connecting bars, anchor rods and sprayed concrete, and form the primary support structure by installing profiled steel arch frames, hanging nets and sprayed concrete construction 4;
[0074] (3) Plain concrete 5 is integrally backfilled on the side of the middle pilot tunnel 1 near the rear tunnel 3;
[0075] (4) The first hole 1 is mechanically excavated by the step method, and the initial support is closed to form a ring;
[0076] (5) The rear tunnel 3 is mechanically excavated by the step method, and the initial support is closed to form a ring.
[0077] Wherein, ...
PUM

Abstract
Description
Claims
Application Information

- R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com