Construction method for steel-concrete arch ring chord member of steel truss arch
A construction method and steel-mixed technology, which is applied in the field of bridge engineering, can solve the problems of insufficient utilization of steel, inability to bear force, and poor economy, so as to reduce the risk of high-altitude operations, increase the horizontal and vertical rigidity, and reduce the weight of steel Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0031] Such as Figure 1-7 As shown, the construction method of the steel-concrete arch ring chord of a steel truss arch according to the present invention comprises the following steps:
[0032] A. The upper chord 1, the web 2 and the lower chord 3 of the hoisting arch ring are assembled by cantilever to form a whole until the arch ring is closed. The two ends are connected to the combination structure 02, and the other end of each combination structure 02 is connected to the steel-concrete structure 03;
[0033] B. Use the box shell steel plate 4 of the upper chord 1 and the lower chord 3 included in the steel-concrete structure 03 as the outer formwork for pouring concrete, from the upper chord 1 and the lower chord 3 tops of the steel-concrete structure 03 The pouring hole 6 pours concrete into the boxes of the upper chord 1 and the lower chord 3 included in the steel-concrete structure 03;
[0034] C. The box shell steel plate 4 of the upper chord 1 and the lower chord ...