Embodiment 1
[0053] A kind of modular building structure, with reference to figure 2 , which includes a house body 1 and a roof 11 arranged above the house body 1 . The house body 1 includes several vertically connected fixing plates, and the fixing plates include several first fixing plates 2 and second fixing plates 3 perpendicular to the first fixing plates 2 .
[0054] refer to figure 2 A locking cover 8 is provided at the seam of the outer side walls of the first fixing plate 2 and the second fixing plate 3, and in this embodiment the locking cover 8 is connected with the first fixing plate 2 and the second fixing plate 3 by screws.
[0055] refer to figure 2 and image 3 A filling layer 81 is bonded to the end surfaces of the locking cover 8 near the first fixing plate 2 and the second fixing plate 3, and the material of the filling layer 81 in this embodiment is preferably sponge.
[0056] refer to image 3 A waterproof layer 82 is bonded between the filling layer 81 and the...
Embodiment 2
[0072] Modular house construction method is characterized in that: comprising the following steps:
[0073] S1. According to the geological inspection report, the ground is leveled, the reinforced concrete belt foundation is poured, and the uplift anchor bolts are pre-embedded at the corners;
[0074] S2. Fix the ground anchor on the anti-lift anchor bolt and tamp it tightly so that the support panel of the ground anchor fits the ground, and then adjust the anchor insert set reasonably according to the height of the ground, so that the ground anchor and the ground are kept level;
[0075] S3. Fix the opening of the channel steel upward on the laid flat structure as a ground beam, and fix the ground beam and the ground through several angle steels;
[0076] S4. Hoist the house body 1 that has been transported to the construction site, and place the house body 1 in the ground beam and fix it with the ground beam; after the installation of the house body 1 is completed, hoist and...