Embodiment 1
[0055] Such as Figure 2-3 As shown, the specific implementation steps are as follows:
[0056] 1) The drilling rig is positioned to construct the borehole 4, the clear distance between the borehole 4 and the pile 3 is 0.2m, the depth of the borehole 4 is about 1m greater than that of the pile 3, and the diameter of the borehole 4 is 110mm;
[0057] 2) A grouting device 5 is installed at the bottom of the grouting pipe 2, and a grouting hole is opened on the grouting device 5. The diameter of the grouting hole is 5 mm. The outer surface of the grouting device 5 is wrapped with iron sheet and rubber. The thickness of the iron sheet is 1 mm, and the thickness of the rubber is 1 mm. , the periphery of the grouting device 5 is wrapped with geotextile, and the length of the wrap is 2m;
[0058] 3) Insert the grouting pipe 2 into the borehole 4, and the depth of the grouting device 5 reaches the bottom of the borehole 4;
[0059] 4) A grouting device 5 is installed at the bottom of ...
Embodiment 2
[0065] Such as Figure 4-5 As shown, the specific implementation steps are as follows:
[0066] 1) The drilling rig is positioned to construct the borehole 4, the clear distance between the borehole 4 and the pile 3 is 0.2m, the depth of the borehole 4 is about 1m greater than that of the pile 3, and the diameter of the borehole 4 is 110mm;
[0067] 2) A grouting device 5 is installed at the bottom of the grouting pipe 2. A grouting hole is opened on the grouting device 5. The diameter of the grouting hole is 5 mm. The outer surface of the grouting device 5 is wrapped with iron sheet and rubber. 1mm, the geotextile is wrapped around the grouting device 5, and the wrapping length is 2m;
[0068] 3) Insert the grouting pipe 2 into the borehole 4, and the depth of the grouting device 5 reaches the bottom of the borehole 4;
[0069] 4) Open the bottom of the plugging pipe 1, insert the plugging pipe 1 into the borehole 4, and the depth is about 2m less than the grouting pipe 2; ...