Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Method for installing post-installed steel beam of basement roof frame

A basement roof and installation method technology, which is applied to the processing of building materials, construction, building construction, etc., can solve the problems of large amount of chiseling and removal, and achieve the effects of shortening the installation period, easy operation, and reducing installation costs

Inactive Publication Date: 2018-12-14
BEIJING SHOUGANG CONSTR GROUP
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The force on the roof of the basement increases. After the design calculation, it is necessary to add steel beams to the roof frame of the basement to strengthen the force on the roof. The main difficulty in installing the rear steel beams is that the concrete roof of the basement frame has been formed, and the normal installation of the steel beams generally needs to be chiseled out. After the steel beam concrete roof is installed from above, the amount of chiseling is very large, such as chiseling the concrete roof, etc.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for installing post-installed steel beam of basement roof frame
  • Method for installing post-installed steel beam of basement roof frame
  • Method for installing post-installed steel beam of basement roof frame

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment approach

[0016] Figure 1-Figure 5 It is a specific embodiment of the present invention. The specific implementation is as follows:

[0017] The first step is to pre-install the concrete roof 2 in the middle of the steel beam 1 in the basement 4 and drill an 80mm round hole 3 with a water drill;

[0018] In the second step, a frock hanger 5 is placed directly above the circular hole 3 of the concrete roof 2, the frock hanger is processed and manufactured on site, and the hoisting guarantees the hoisting strength;

[0019] The third step is to fix the chain-reversing sling 6 on the tooling hanger 5, and vertically pass through the 80mm round hole 3 of the concrete roof, and the sling 7 fixes the steel beam 8 to be installed below the basement 4 (the steel beam is transported from the entrance of the basement by means of transportation) transported to the place directly below the installation location in advance);

[0020] In the fourth step, the tooling hanger 5 is lifted by the hois...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for installing a post-installed steel beam of a basement roof frame, and belongs to the technical field of installation of a post-installed steel beam of a basement roof frame. The method comprises the steps of drilling an 80mm round hole (3) in a concrete roof (2) in the middle position of a pre-installed steel beam (1) of a basement (4), and placing a tooling hanger (5) right above the concrete roof (2) and the round hole (3); fixing a chain hoist cable tool (6) on the tooling hanger (5) to vertically pass through the 80mm round hole (3) of the concrete roof,and fixing a to-be-installed steel beam (8) at a lower portion of the basement (4) by a cable tool (7); pulling and lifting the steel beam (8) by the chain hoist cable tool (7) on the tooling hanger(5) for installation in place. The method has the advantages that the operation is easy, the concrete roof is prevented from being removed, the installation period is shortened, the installation quality is ensured, the installation cost is greatly reduced, and good economic benefits are obtained.

Description

technical field [0001] The invention belongs to the technical field of installing a rear steel beam of a basement roof frame, and in particular provides a method for installing a rear steel beam of a basement roof frame. Background technique [0002] A multi-storey steel frame structure building with a basement, due to the addition of some equipment on the first floor in the later period, [0003] The force on the roof of the basement increases. After the design calculation, it is necessary to add steel beams to the roof frame of the basement to strengthen the force on the roof. The main difficulty in the installation of the rear steel beams is that the concrete roof of the basement frame has been formed, and the normal installation of the steel beams generally needs to be chiseled out. After the steel girder concrete roof is installed from above, the amount of chiseling is very large, such as chiseling the concrete roof and so on. Contents of the invention [0004] The p...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E04G21/14
CPCE04G21/14
Inventor 王放
Owner BEIJING SHOUGANG CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products