Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

230results about How to "Shorten the installation period" patented technology

On-line assembling entirety on-position assembling method of edge mill

The invention relates to a method for the integral falling installation of on-line assembly of a vertical miller, belonging to the technical field of installation of large-sale equipment. The installing steps comprise the installation and transverse alignment of the soleplate of the vertical miller, the arrangement of an assembling and falling device, the assembly of an upper beam and a lower beam of a stander outlet, the slippage of a stander torii, the assembly and fixation of an upper beam and a lower beam of a stander inlet; the integral falling installation position of the stander and the installation of a rolling mill transmission device. The invention has the advantages that a special lifting device is not needed to be manufactured; the architecture design of workshops is not needed; the constructing investment is not increased; a field for building a precision assembly platform is not needed to be reserved in a main workshop; the time for the vertical miller equipment to enter the arena is not limited, so the installation cost can be greatly reduced, the labor intensity is lightened, and the time limit for the installation is shortened; and the invention is applied to the projects of installation and repairing of vertical millers attached to hot plate or band roughing mills.
Owner:BEIJING SHOUGANG CONSTR GROUP +1

Installation method of special-shaped and curved-surface suspension type steel structure system

The invention belongs to the technical field of steel structure construction, and particularly relates to an installation method of a special-shaped and curved-surface suspension type steel structuresystem. The problems are solved that the construction precision of a traditional installation method is difficult to guarantee, the construction period is long, a large amount of cost needs to be invested in scaffold and inclined suspender layer-by-layer hoisting, and many high-altitude hidden dangers exist. The special-shaped and curved-surface suspension type steel structure system comprises a core cylinder, a giant truss, a temporary support, an inclined suspender and beams of all floors. The installation method comprises the following steps that S1, the core cylinder is constructed; S2, the temporary support is installed; S3, the giant truss is assembled on the ground; S4, the giant truss is hoisted; S5, the inclined suspender is installed; S6, the temporary support is unloaded; S7, the beams of all the floors are hoisted; and S8, the displacement of the giant truss is monitored in the steps of S4-S7. According to the installation method, the construction precision is guaranteed, the installation efficiency is high, the installation construction period is shortened, and the operation safety risk is reduced. The erection and hoisting cost of a scaffold is saved, the high-altitude butting joints are reduced, the near-edge protection cost is reduced, and therefore the construction cost is reduced.
Owner:CHINA SHANXI SIJIAN GRP

Installation method of ultra-large diameter pressure steel pipe on inclined shaft lower curved section

ActiveCN107588233ARealize secondary assembly weldingMeet the requirements of mechanized assembly of stiffening ringsPipe laying and repairWelding/cutting auxillary devicesWeldingCivil engineering
The invention discloses an installation method of an ultra-large diameter pressure steel pipe on the inclined shaft lower curved section. The method comprises the steps that the ultra-large diameter pressure steel pipe is assembled, steel pipe sections are transported in an adit, a formed steel pipe is positioned and installed on the inclined shaft lower curved section, the positioning and installing processes comprise the steps that a ground anchor and a traction steel cable are arranged on the inclined shaft upper horizontal section, the traction steel cable is connected with a traction climbing device and the ground anchor, and the traction climbing device is arranged at the lower end of the first section of the lower curved section pressure steel pipe; all single sections of the lowercurved section pressure steel pipe are subjected to assembly welding and climbing positioning fixation in sequence, and then the traction climbing device is removed to complete installation. Accordingly, traditional production line operation arrangement can be effectively simplified, hole assembly temporary facility arrangement is simplified, adit and main hole excavation sections are reduced, the pipe section assembly land area is reduced, land requirements for finished product stacking are canceled, pipe section secondary assembly welding once forming is achieved, the installation precisionis improved through mechanical assembly welding, hoisting and turning over are conducted without relying on an indigenous method, the safety risk is lowered, the installation construction period is shortened, the number of installation personnel is reduced, and the investment is saved.
Owner:SINOHYDRO BUREAU 7 CO LTD

Pumped storage power plant tail water retained rock step blasting safety protection method

The invention discloses a pumped storage power plant tail water retained rock step blasting safety protection method, and relates to an underwater rock step blasting safety protection method. A bladder curtain and porous stoplog gates are constructed outside a rock step to be blasted; the bladder curtain consists of a plurality of steel pipes; two rows of holes are bored on each steel pipe; and each steel pipe is connected with an air pipe of an air compressor. The porous stoplog gates consist of a steel frame and bamboo rafts; I sections are arranged on both sides of the stoplog gate of eachhole; the two sides of each I section are fixed on round flow splitting support piers through steel plates and expansion bolts; each stoplog gate is in welded connection through channel steel, the I sections and angle bars; a layer of vertical bamboo gangway is spread on the water inlet surfaces of the stoplog gates; and simultaneously safety nets are arranged on the tops of flow splitting support piers on the top and both sides of a single hole stoplog gate. The method adopts the proposal of arranging the bladder curtain plus the steel frame, the bamboo rafts and the safety nets to replace aproposal of the stoplog gate, has scientific and reasonable design, protects a trash rack and a tail gate against the damage and the influence of the blasting, and brings about easy spoil removal, short manufacturing and installation time limits, and low manufacturing, installation and demolition cost.
Owner:STATE GRID CORP OF CHINA +2

Elevator assembled by utilizing combination type derrick

InactiveCN102060222ASave the trouble of civil constructionFlexible assemblyElevatorsBuilding liftsEngineeringWork time
The invention discloses an elevator assembled by utilizing combination type derricks, relating to hoisting equipment. A hoistway wall of the elevator is formed by assembling more than two derricks, wherein each derrick comprises stand columns, a door beam, a front beam, a back beam, a left beam, a right beam, a cage guide rail and a counter-weight guide rail, wherein the four stand columns are distributed at four corners of the derrick, and connection seats are horizontally and fixedly arranged at the top end and the bottom end of each stand column and provided with connection holes; two ends of the door beam, the front beam, the back beam, the left beam and the right beam are transversely and respectively connected with the stand columns; and the cage guide rail and the counter-weight guide rail are respectively installed in the middle parts and the inner sides of the back ends of the left beam and the right beam. Because the derricks can be produced in a standardized way in a factory and assembled on site, the working time limit can be shortened, the cost can be lowered, the manufacturing cost can be reduced, and the installation efficiency and quality can be improved; and because the derricks are matched with an up-down door-opening and closing mechanism, the influence of the installed elevator on ventilation and daylighting of a household can be reduced. The elevator assembled by utilizing the combination type derricks is mainly used for places of low storey dwelling houses, in particular to the old style low storey dwelling houses of less than 9 storeys.
Owner:张向阳

Self-compensating fastening type large-diameter fast joint

The invention relates to a self-compensating fastening large-caliber fast adaptor which is used for butt jointing of two pipes and solves the defects of high cost and poor practicability in the prior art. The invention is characterized in that: the outer circumference of pipe fittings is encircled by a rubber sealing boot 2, a convex ring of which is arranged among the pipe fittings. Left and right sleeves 3 and 4 are respectively sheathed on the pipe fittings, and pressed on the outer surface of the rubber sealing boot 2. A trough 9 of the left sleeve 3 is meshed with a projection 12 of the right sleeve 4. A cotter pin 8 fixedly locks the left and right sleeves 3 and 4. A claw 5 is provided with a pointed teeth on the concave surface, arranged in dovetail inner cone troughs 11 and 14 in the left and right sleeves 3 and 4, pasted on the outer wall of the pipe fittings, can slide along the axial direction of the pipe fittings and concentrically contract to occlude and tighten the pipe fittings. The fast adaptor is high, middle and low pressure resistant. The self-compensating fastening omni-directional secure seal with firm soft syncretic is provided without welding or flange type, not being opened with trench type, and not being provided with a compensator additionally, thereby saving labor and time, especially under the condition of severe environment, the fast adaptor of the invention has the advantages of being convenient and fast, low cost, energy saving and environmental protection. The fast adaptor of the invention is used for connecting two pipes through which the fluid is to be conveyed.
Owner:王甲南

Assembly method of bridge-building machine at exit of tunnel connected with bridge

The invention discloses the field of bridge construction, and particularly relates to an assembly method of a bridge-building machine at an exit of a tunnel connected with a bridge. The assembly method of the bridge-building machine mainly comprises the following steps of: setting aside a working site; installing sliding devices at the bottoms of a second main beam and a third main beam; installing an electric running mechanism for a rear support leg of a first main beam of the bridge-building machine at the bottoms of an inverted arch of the tunnel, and installing a front support leg on a No. 0 platform; assembling the main beams and guide beams through a running motor in the electric running mechanism for the rear support leg, and returning into the tunnel; and moving the whole assembled structure of the main beams and the guide beams out of the tunnel through the running motor in the electric running mechanism for the rear support leg. By adopting the assembly method, large-scale backfilling, flattening and hardening are not needed for an assembly site, large quantities of earthwork and stonework engineering and shifts for operation of large-tonnage lifting devices can be saved, and the installation period can be greatly shortened.
Owner:CHINA RAILWAY NO 2 ENG GRP CO LTD +1

Method for mounting seat pulp cushion plates of petrochemical static equipment and foundation structure

The invention discloses a method for mounting seat pulp cushion plates of petrochemical static equipment and a foundation structure. The method includes that a plurality of concrete piers with cushion plates are manufactured on a concrete base, the minimum area of each single cushion plate is computed according to the sum of the weight of the equipment and pre-tightening force of anchor bolts, load added on the cushion plate and compressive strength of selective concrete, the concrete piers are trapezoidal tables, the seat pulp cushion plates are arranged on tops of the concrete piers, and surfaces of the cushion plates are positioned on the same horizontal plane. The equipment is seated on the cushion plates of the concrete piers by means of hoisting, and the various anchor bolts are fastened. A secondary grouting layer is formed by means of secondary grouting for a space between the bottom of the equipment and the concrete base. The trapezoidal table concrete piers which are positioned below a reinforcing plate of the equipment are arranged on the concrete base of the foundation structure, the cushion plates are disposed on the tops of the piers, and the surfaces of the cushion plates of the piers are positioned on the same horizontal plane. The secondary grouting layer is disposed between the bottom of the equipment and the concrete base. The method and the foundation structure have the advantages that wedge liners are omitted, materials are saved, the cushion plates of the concrete piers are integrally connected with the base, installation is carried out conveniently, installation quality is improved, and installation work period is shortened.
Owner:BC P INC CHINA NAT PETROLEUM CORP +1

Steel-sleeve steel steam insulation pipe and rolling supporting mechanism thereof

The invention relates to a steel-sleeve steel steam insulation pipe and a rolling supporting mechanism thereof, wherein the nominal diameter of an inner sleeve steel pipe of the steel-sleeve steel steam insulation pipe is DN 250-DN 500. The rolling supporting mechanism comprises an upper steel hoop, a lower steel hoop, two upper idler wheels and two lower idler wheels, wherein the upper idler wheels and the lower idler wheels are respectively arranged on the upper steel hoop and on the lower steel hoop and distributed symmetrically; the end parts of the upper steel hoop and the lower steel hoop are clamped tightly by bolts; and when the axes of the inner sleeve steel pipe and an outer sleeve steel pipe are overlapped, the two lower idler wheels and the inner wall of the outer sleeve steelpipe are contacted in a rolling friction way, and fit-up gaps are left between the upper idler wheels and the inner wall of the outer sleeve steel pipe. The steel-sleeve steel steam insulation pipe comprises the inner sleeve steel pipe, the outer inner sleeve steel pipe, the rolling supporting mechanism, insulation material and heat-preservation material, wherein the external diameter of the heat-preservation layer is smaller than the internal diameter of the outer sleeve steel pipe and an air layer is formed between the heat-preservation layer and the sleeve steel pipe. The rolling supportingmechanism has small friction force, therefore, the stress of the rolling supporting mechanism and the inner sleeve steel pipe is reduced.
Owner:刘毅 +1

Ultra-large-diameter steel penstock installation method

InactiveCN107503333ARealize secondary assembly weldingMeet the requirements of mechanized assembly of stiffening ringsFinal product manufactureWater-power plantsProduction linePenstock
The invention discloses an ultra-large-diameter steel penstock installation construction technique. An installation method comprises the steps that ultra-large-diameter steel penstocks are coupled on site, specifically, tiles split into three flaps are rounded, single-section steel penstocks are assembled into multi-section steel penstock sets through assembling and welding, and stiffening rings are additionally welded to the multi-section steel penstock sets; the coupled steel penstock sections are transported in an adit, specifically, rails are prefabricated and paved in the adit, and the steel penstocks are transported to an installation station through a separable trolley; and the formed steel penstocks are positioned and installed, specifically, in the installation station, after steel penstock bodies are regulated to the installation height and fixed through a separable trolley jacking device, the trolley is removed, and integral installation of the multiple steel penstock sections is achieved. According to the ultra-large-diameter steel penstock installation construction technique, the operation layout of a traditional production line is effectively simplified, temporary assembling facilities inside the adit are simplified, the excavated sections of branched holes and the excavated sections of a main hole are decreased, the occupied area for steel penstock section assembling is decreased, and the requirements of a place where finished products can be stacked are eliminated; steel penstock sections are formed at a time during secondary assembling and welding, and the installation precision is improved through mechanical assembling and welding; and the installation construction technique does not rely on traditional lifting and turning modes any more, the safety risk is lowered, the installation construction period is shortened, the installation personnel number is decreased, and investment is reduced.
Owner:SINOHYDRO BUREAU 7 CO LTD

Process for heating sleeve shaft through magnetic induction by large ring component

The invention relates to a process for heating a sleeve through magnetic induction by a large ring component. Finish machining is conducted on the ring component until certain size of the ring component is reached before shrinkage fit. In order to avoid thermal consumption after heating and prevent the surface of a ring from being burned due to the fact of partial overheat, asbestos cloth is coated and surrounds the outer surface of the ring, induction coils are wound on the outer surface of the ring, the ring is lifted above a rotating shaft through a crane, and after the ring is heated, when the minimum size of the ring is detected to meet requirements of a drawing through a measuring bar, the ring is smoothly dropped, and the shrinkage fit is conducted on the ring. After the ring is cooled to room temperature, size difference of an outer ring of the ring before the shrinkage fit and after the shrinkage fit is not larger than 0.02 millimeter. After the shrinkage fit is finished for the first time, the ring does not need machining a large equipment for the second time again after the shrinkage fit, the lowest heating temperature is controlled through intermediate-frequency electromagnetic induction heating, and deformation of the ring is small after the shrinkage fit after the ring is heated. The process for heating the sleeve shaft through magnetic induction by the large ring component has the advantages of being simple in operation, simple in required equipment, low in manufacturing cost, short in working period and the like, can save a large amount of cost from secondary machining to large-equipment machining, and is very high in application value.
Owner:HARBIN ELECTRIC MASCH CO LTD

Steel-sleeve steel steam insulation pipe and rolling supporting mechanism thereof

The invention relates to a steel-sleeve steel steam insulation pipe and a rolling supporting mechanism thereof, wherein the nominal diameter of an inner sleeve steel pipe of the steel-sleeve steam insulation pipe is DN 600-DN 700. The rolling supporting mechanism comprises an upper steel hoop, a lower steel hoop, two upper idler wheels arranged on the upper steel hoop and distributed symmetrically, and four lower idler wheels arranged on the lower steel hoop and distributed symmetrically, wherein the four lower idler wheels are evenly divided into two groups; the end parts of the upper steel hoop and the lower steel hoop are connected by bolts; and when the axes of the inner sleeve steel pipe and an outer sleeve steel pipe are overlapped, the four lower idler wheels and the inner wall of the outer sleeve steel pipe are contacted in a rolling friction way, and gaps are left between the two upper idler wheels and the inner wall of the outer sleeve steel pipe. The steel-sleeve steel steaminsulation pipe comprises the rolling supporting mechanism and also comprises insulation material positioned between the rolling supporting mechanism and the inner sleeve steel pipe, heat-preservation material with the external diameter smaller than the internal diameter of the outer sleeve steel pipe, an air evaporation valve arranged on the outer sleeve steel pipe, and erosion resistant coatingsleeved outside the outer sleeve steel pipe. The rolling supporting mechanism has small friction force, therefore, the stress of the rolling supporting mechanism and the inner sleeve steel pipe is reduced.
Owner:刘毅 +1

Self-installed ocean floor drilling template and installation method thereof

The invention discloses a self-installed ocean floor drilling template and an installation method thereof. The self-installed ocean floor drilling template comprises a pile foundation, a guide post and a wellhead guide framework, the pile foundation is a suction pile, the suction pile and the guide post are connected into an integral structure through the wellhead guide framework, the integral structure can be conveniently leveled in the suction immersion process, and a pump opening is formed in the wellhead guide framework and used for installing a submersible pump for extracting water in the suction pile. The self-installed ocean floor drilling template has the advantages that the self-installed ocean floor drilling template can be assisted in underwater towing by a buoy and can be lowered in water by an inherent small lifting device on a ship after reaching an installation position, the template can be leveled in the negative pressure immersion process of the suction pile, piling operation and grouting operation are omitted, a special leveling device for leveling operation is omitted, installation procedures of an offshore drilling template are simplified, offshore installation period is shortened, and construction cost is reduced.
Owner:CHINA NAT OFFSHORE OIL CORP +1

Self-compensating direct quick-connection pipeline

A self-compensating direct quick-connection pipeline comprises a left head 1, a pipeline 2, a right head 3 and a rubber sealing ring 4, is used for the contra-aperture quick connection of pipelines, and solves the defects that the prior pipe connection technique has high cost and poor practicability, wherein the left head 1 is inserted into and spirally buckled with the inner cavity of the right head 3, the rubber sealing ring 4 is compressed and sealed therein. The pipe fittings and valves of the self-compensating direct quick-connection pipeline are resistant to high pressure, medium pressure and low pressure, do not pull screw thread, are not welded, are not in flange mode, channeling mode and electric heating melting mode, are not additionally added with a compensator, are capable of realizing direct contra-aperture quick connection of the pipelines in severe environment conditions, such as lofty mountains and steep hills, deserts, water of rivers, lakes and seas, narrow space, windy, rainy, high-temperature and chill weather, combustible and explosive places, provide self-compensating lockable rigid-flexible omnibearing safety sealing, save labor and time, and have low cost, high efficiency, energy conservation and environment protection. The invention provides the self-compensating direct quick-connection pipeline for conveying fluids.
Owner:王甲南

Integral hydraulic jacking inverted construction method of large converter

The invention discloses an integral hydraulic jacking inverted construction method of a large converter, comprising the following steps: 1) in an additive bay, fixedly installing a converter shell bracket and an integral bracket on a ladle car, and building an erecting stage on the integral bracket; 2) successively inverting and hoisting the welded converter shell and backing ring which are welded into a whole on the converter shell bracket and the integral bracket, respectively adjusting the positions of the converter shell and the backing ring by a hydraulic jack to cause the relative positions of the converter shell and the backing ring to satisfy a design requirement, and ensuring that a center elevation is bigger than a designed elevation; 3) installing and hanging; 4) moving the ladle car to transport the converter to the base of the converter, finishing installation of a trunnion bearing pedestal before transporting; and 5) lowering the backing ring to cause the bearing pedestal to land on the base, and fixing after adjusting. In the invention, the phenomenon that the additive bay of a converter workshop uses a large crane is avoided, a jack is adopted to adjust the positions of the backing ring and the converter shell, and construction is convenient. The converter is assembled in the mode that the backing ring and the converter shell are inverted, and hoisting and welding are easy to operate.
Owner:TIANJIN 20 CONSTR

All-welded box girder combination section constructing method

The invention relates to an all-welded box girder combination section constructing method. The method comprises the specific steps that a girder is divided by making the distance length of two sections serve as one novel box girder combination section, plate units of sectional unit parts are manufactured, a girder lower chord is welded to a lower bridge surface steel box, a girder upper chord is welded to an upper bridge surface panel, a transverse bracing system is welded to a girder vertical rod, the girder vertical rod and an inclined rod are welded to the girder lower chord and the girder upper chord, and the novel box girder combination sections are formed; trial splicing is performed on adjacent novel box girder combination sections on a preset trial assembly platform, and anticorrosion coating is performed on the outer surface. All-welded box girder combinations are welded in place according to a construction order on a bridging construction site. According to the method, the girder is designed into the all-welded box girder combination sections, few hanging units are used, durability of the girder is improved, maintaining workloads during the later period are reduced, site construction is simplified, work efficiency is improved, and an installation period is shortened; the appearance is beautiful, and durability is good. The method has been successfully applied to the Shanghai-to-Nantong railway Yangtze river highway-railway dual-purpose great bridge engineering.
Owner:CHINA MAJOR BRIDGE ENERGINEERING +1

Device used for shear wall elevation and levelness control and use method thereof

The invention discloses a device used for shear wall elevation and levelness control and a use method thereof. The device comprises a levelness control plate, fine adjusting supporting rods are connected to the end face of one side of the levelness control plate, a threaded part is arranged at the end, far away from the levelness control plate, of each fine adjusting supporting rod, and the fine adjusting supporting rods are movably connected to fine adjusting supporting rod support bases. The method includes the steps that S1, when a prefabricated shear wall is produced and manufactured, the fine adjusting supporting rod support bases are pre-buried; S2, the fine adjusting supporting rods are screwed into the fine adjusting supporting rod support bases and adjusted, so that the height of the end face of the top of the levelness control plate is consistent with the height of control elevation of the bottom of a prefabricated wallboard on the upper layer; S3, after concrete reaches certain strength, it is only needed that the prefabricated shear wall wallboard on the upper layer is directly placed on the levelness control plate. The elevation and levelness of the wallboard are effectively controlled, the installation period of the prefabricated wallboard is shortened, labor cost is reduced, and meanwhile wet construction workloads of operators in a construction site are reduced.
Owner:CHINA MCC17 GRP

Device for fast mounting subway tunnel electromechanical equipment and pipelines

The invention relates to the technical field of tunnel construction, in particular to the mounting of subway tunnel electromechanical equipment and pipelines, and specifically discloses a device for fast mounting the subway tunnel electromechanical equipment and pipelines. The device comprises a tunnel segment, an embedded anchor bolt, a plurality of external anti-seismic slide grooves and a mounting support, wherein the embedded anchor bolt comprises a segment positioning device and an anchor bolt body, and each external anti-seismic slide groove comprises a C-shaped toothed slide groove body and at least two mounting bases. The device has the advantages that the embedded bolt is arranged in the tunnel segment to replace a traditional perforation and steel bar embedding process, dense perforation of a tunnel structure is not needed, tunnel structure zero damage is guaranteed, tunnel structure integrity is protected, the service life of the tunnel structure is prolonged greatly, and subway operation safety is guaranteed; damage to construction worker health is avoided; the device is simple in embedding construction, fast in mounting, capable of greatly reducing the mounting period of the electromechanical equipment and pipelines and capable of greatly lowering construction and maintenance costs.
Owner:康元轨道交通科技(福建)有限公司

Offshore wind turbine installation method and installation system

The invention belongs to the technical field of marine machinery, relates to an offshore wind turbine installation method and installation system and aims at solving the problems of large difficulty and the like during butt joint installation of a wind turbine in the prior art. A wind turbine comprises an engine room, a tower barrel and a blade. The installation system comprises a fan mounting ship; the fan mounting ship is provided with a rotating table which can swing between a horizontal position and a vertical position in a reciprocating manner; the rotating table is provided with a translation device capable of moving in the reciprocating manner in a horizontal direction; and the translation device is provided with a fastening device capable of fixing the engine room, the tower barreland the blade and a sliding rail capable of being aligned with a mounting base. For the offshore wind turbine installation method and installation system, when the tower barrel, the engine room and the blade are installed, the sliding rail is designed, so that shaking caused by a wind force during the installation process can be effectively avoided, the butt joint precision during installation iseffectively improved, the butt joint difficulty is lowered, the installation efficiency is improved, and the installation period is shortened.
Owner:ZHEJIANG OCEAN UNIV

Rapidly-installed photovoltaic module integrated board and installation method

The invention provides a rapidly-installed photovoltaic module integrated board and an installation method. The rapidly-installed photovoltaic module integrated board comprises a plurality of photovoltaic modules, a foldable integrated board fixing frame and a positioning installation device. The foldable integrated board fixing frame comprises a fixing frame component and a positioning hinge. Thepositioning installation device comprises at least two groups of positioning brackets and a driving part; the driving part drives the positioning brackets to move; a linkage mechanism is formed between the positioning brackets and the foldable integrated board fixing frame; and unfolding and folding of the foldable integrated board fixing frame are controlled through the positioning brackets. A plurality of photovoltaic module single boards connected in series are connected through a foldable integrated board fixing frame to form an integrated unit, the structural shape of the integrated unitafter being unfolded is controlled through the positioning angle of the positioning hinge, and the integrated unit is folded to form the size of one photovoltaic module single board or form a plane structure or a curved surface structure after being unfolded. Thus, a photovoltaic cell panel is protected, the transportation and installation efficiency is improved, and the construction cost of a photovoltaic power station is reduced.
Owner:SHANGHAI JIAO TONG UNIV +1
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products