Secondary launching construction method for overall station-crossing of sliding steel sleeve and shield tunneling machine
A construction method and a technology of steel sleeves, which are applied in wellbore lining, earthwork drilling, tunnel lining, etc., can solve the problems of large tunnel structure influence, large construction volume, and long time consumption, and achieve construction safety, save construction period, and reduce cost effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0051] The present invention will be further described below in conjunction with the accompanying drawings of the description.
[0052] The construction method for the second initiation of the overall passing of the sliding steel sleeve shield machine 3 includes the following steps:
[0053] Step 1, construction preparation operation:
[0054] Step 1.1, review and measure the headroom size of station 1, and require the headroom size of station 1 to be larger than the size of the steel sleeve and reserve the required working space;
[0055] Step 1.2, use a level measuring instrument to level the well at the receiving end of the shield tunneling machine, install the steel sleeve, tunnel the shield machine 3 into the steel sleeve, assemble the last segment and perform grouting to complete the receiving of the shield tunnel;
[0056] Identify the cables and pipelines on the shield machine 3, disconnect the cables and pipelines between the shield machine 3 and the supporting troll...