The Method of Excavation, Excavation, Support and Brush Expansion in Fully Mechanized Caving Working Face with High Stress Water Rich Roof

A fully-mechanized caving face and high-stress technology, which is applied to earthwork drilling, mining equipment, tunnels, etc., can solve the problems of difficult roof maintenance, hidden dangers of roof fall, and long roof exposure time, so as to improve the safety of cutting holes, brush expansion, Good technical and economic benefits, good promotion and application value effect

Active Publication Date: 2020-11-10
SHANDONG XINJULONG ENERGY
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In mining areas where the depth of the coal mine is relatively deep, when the comprehensive top-coal caving mining method is adopted, due to the high ground stress, large rock burst, and strong water-rich roof sandstone, it is necessary to use a high-resistance comprehensive top-coal caving support (referred to as high resistance) fully-mechanized caving support); due to the large size of the support, it is necessary to expand the original incision brush to a net width of more than 10m when installing the support; this kind of large-span incision brush expansion has the following problems: due to the original ground stress and structural stress of the roadway Due to the influence of the superimposed stress field, and the overlying rock layer on the roof is a top-coal composite roof with strong water richness, it is difficult to maintain the roof. In addition, it usually takes several months to install the brackets, and the roof is exposed for a long time, which is easy to cause roadway deformation (bottom Drums, ribs, roof sinking, etc.), there is a serious risk of roof fall
At present, there are few domestic researches on the technology of high-stress top-coal cutting hole brush expansion, and no relatively perfect method has been found to solve the above problems.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • The Method of Excavation, Excavation, Support and Brush Expansion in Fully Mechanized Caving Working Face with High Stress Water Rich Roof
  • The Method of Excavation, Excavation, Support and Brush Expansion in Fully Mechanized Caving Working Face with High Stress Water Rich Roof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] refer to figure 1 figure 2 The steps of the implementation of the present invention are further described.

[0027] A method for digging, digging, branching and brushing expansion of fully mechanized caving working faces with high-stress water-rich roofs, the steps are as follows:

[0028] The first step, eye-cut excavation and support

[0029] First, adopt the existing construction method to excavate the cutout 1, and support it while digging until the cutout is penetrated to form a return air condition; the design section of the cutout is a rectangular section with a clear width of 5.0m and a clear height of 3.7m to meet the ventilation requirements; Among them, the support methods are: permanent support of the roof and Waibang 14, and temporary support of Neibang, the details are as follows:

[0030] 1) Drill anchor holes on the top plate and the outer wall 14, the anchor hole spacing is 500-600mm, the row spacing is 600-800mm, and the hole depth is 2500mm; after...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a high-stress water-rich roof fully mechanized caving face open-off cut, advancing and supporting and brushing expansion method. The high-stress water-rich roof fully mechanized caving face open-off cut, advancing and supporting and brushing expansion method includes the following steps that first, open-off cut, advancing and supporting are conducted, on the basis of penetrating an open-off cut and completing supporting, then an anchor cable beam is installed to strengthen supporting simultaneously, a mechanized caving face frame rear scraper conveyor is arranged on the rear part of the anchor cable beam in a closing mode, and installation and arrangement are conducted simultaneously; second, open-off cut, brushing expansion and pre-supporting are conducted; and third, brushing expansion and assembling high resistance fully mechanized caving support parallel operation are conducted. According to the method, advancing and supporting are coordinated with support installation parallel cooperation and connected to technology, the problems that the installation of a fully mechanized caving hydraulic support is slow, the length of a hydraulic support trailing head is long, the span of a lane is large, and construction hidden risks exist are effectively solved, the safety of open-off cut and brush expansion in high stress area can be actually improved, and the purpose of lane advancing in a safe and quick mode is achieved.

Description

technical field [0001] The invention relates to the technical field of coal mining. Background technique [0002] During coal mining, it is necessary to prepare the roadway in advance for the working face in the mining area, including developing a return airway (track roadway), an air inlet roadway (belt roadway) and a cutout; the cutout is the roadway connecting the inlet and return airway, All the equipment (mainly the shearer and support) of the coal mining face are arranged in this space, and the general cutting eye width is designed to be about 5m. In mining areas where the depth of the coal mine is relatively deep, when the comprehensive top-coal caving mining method is adopted, due to the high ground stress, large rock burst, and strong water-rich roof sandstone, it is necessary to use a high-resistance comprehensive top-coal caving support (referred to as high resistance) fully-mechanized caving support); due to the large size of the support, it is necessary to expa...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/00E21D9/01E21D20/02
CPCE21D9/00E21D9/01E21D20/025
Inventor 刘小龙王岳高翔
Owner SHANDONG XINJULONG ENERGY