Automatic work permission system and method for distribution network maintenance
An automatic work and distribution network technology, applied in the field of electric power, can solve the problems of distribution network dispatchers' work omissions, operational errors, endangering personal and power grid equipment safety, etc., and achieve the effect of improving work efficiency, power supply reliability and reducing workload
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] Such as figure 1 As shown, an automatic work permit system for distribution network maintenance includes a data reading module, a distribution network maintenance list module, a data storage module, a start application module, a start permission module, a completion application module, a completion termination module, and a reminder module;
[0036] The data reading module is used to read the distribution network maintenance list data in the power network and transmit the data to the distribution network maintenance list list module;
[0037] The start-of-work application module is used to submit a start-of-work application request to the start-of-work permit module;
[0038] The start-of-construction permit module is used to automatically permit the start-of-construction application request;
[0039] The completion application module is used to submit the completion application request to the completion completion module;
[0040] The completion termination module is...
Embodiment 2
[0049] Such as figure 2 As shown, the present invention also provides an automatic work permit method for distribution network maintenance. The method is based on the above-mentioned system and includes the following steps:
[0050] Step S1: The data reading module reads the maintenance order data and operation ticket data from the power system, and the distribution network maintenance list module generates a distribution network maintenance list list, and the outage link in the four links of the work progress in the distribution network maintenance list list The status of the power outage operation ticket associated with the distribution network maintenance sheet has not been filed; the status of the start link is application for start; the status of the completion link is not applied for completion; ;
[0051] Step S2: The distribution network dispatcher orders the on-site personnel to operate according to the operation item of the power outage operation ticket associated ...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com