BIM5D-based project construction fine management method

A refined management, BIM-5D technology, applied in office automation, data processing applications, instruments, etc., can solve the problems of lagging construction progress, difficult construction, and poor communication.

Inactive Publication Date: 2020-04-10
CCCC SECOND HARBOR CONSULTANTS CO LTD
View PDF3 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the progress of society, construction projects are developing extremely rapidly, and the scale of the entire building is also expanding, and the subsequent construction period of the project is getting longer and longer, making the entire construction more and more difficult. , structure, and function diversification, and the influence of various factors during the construction project management period is gradually increasing. These influencing factors directly make the construction progress, quality, and economic benefits of the construction party unable to be guaranteed.
[0003] The traditional construction project management period is mainly formed by combining the construction organization, scale, and characteristics of the project. The modular management method, the communication between different module areas is relatively obvious, resulting in the information connection and coordination between the entire construction process. Coordination is extremely limited, which in turn leads to information asymmetry and construction errors. The construction progress of the corresponding project is lagging behind and the construction quality cannot be guaranteed. At the same time, the construction cost continues to increase, which directly hinders the development of the entire construction industry.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • BIM5D-based project construction fine management method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation manners of the present invention will now be described in detail with reference to the accompanying drawings.

[0024] Building Information Modeling (Building Information Modeling) is a new tool for architecture, engineering and civil engineering. The term Building Information Modeling or Building Information Modeling was coined by Autodesk. It is used to describe those computer-aided designs that are mainly three-dimensional graphics, object-oriented, and architecture-related. At the beginning, this concept was promoted by Jerry Laiserin to the public with the technology provided by Autodesk, Bentley Systems Software, and Graphisoft.

[0025] The core of BIM is to establish a virtual three-dimensional model of architectural engineering and use digital technology to provide a complete architectural engineering information librar...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a BIM5D-based project construction fine management method. The method specifically comprises the following steps that: the BIM model of a target project is established; the engineering data are inputted into a BIM informatization project management system with a use function; the BIM model is associated with the engineering data, so that BIM5D basic data can be formed; the planned output value of each piece of work in a progress plan is set; the progress plan is submitted to a supervisor and an owner so as to be audited, and the progress plan passing the auditing is set to be a current progress plan; progress completion conditions are put into statistics; earned value key parameters are automatically calculated; and BIM-5D simulation is carried out, project evolution, project progress and investment change conditions are displayed to a project manager, and the manager can make project cost, progress and quality management decisions conveniently. With the method of the invention adopted, a complete set of scientific, specific, accurate and realizable project construction fine management method is formed.

Description

technical field [0001] The invention relates to the field of engineering project management, in particular to a method for refined management of project construction based on BIM5D. Background technique [0002] With the progress of society, construction projects are developing extremely rapidly, and the scale of the entire building is also expanding, and the subsequent construction period of the project is getting longer and longer, making the entire construction more and more difficult. Due to the diversification of structure and function, the influence of various factors during the construction project management period has gradually increased. These influencing factors directly make the construction progress, quality and economic benefits of the construction party unable to be guaranteed. [0003] The traditional construction project management period is mainly formed by combining the construction organization, scale, and characteristics of the project. The modular manag...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06G06Q10/10G06Q50/08
CPCG06Q10/067G06Q10/103G06Q50/08
Inventor 樊金甲潘国华宋叶青魏世桥孔增增孟成成龚赞杨建峰
Owner CCCC SECOND HARBOR CONSULTANTS CO LTD