A Portable Base and Fully Hydraulic Tunnel Drilling Rig

A portable drilling rig technology, applied in the field of geological exploration and drilling engineering, can solve the problems of long time consumption, unenvironmental protection of materials, disturbance, etc., and achieve the effect of reasonable structural design and strong practicability

Active Publication Date: 2021-06-01
内蒙古山金地质矿产勘查有限公司
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

It takes a long time to build cement piles, and it takes an average of 2.5 days to move and install the drilling rig, including 1 day to wait for the cement to solidify, and 1 day to restore the site and clean the cement piles
2. Limitations of green exploration
The materials used are not environmentally friendly, and the soil needs to be stripped, directly disturbing and affecting the original vegetation layer, which does not meet the requirements of green exploration, and cannot be buried on site after the final hole, and needs to be cleaned and transported
3. Economic and practical limitations
[0006] The construction time is too long, not environmentally friendly, the cost is high, and it can only be used with fixed models

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A Portable Base and Fully Hydraulic Tunnel Drilling Rig
  • A Portable Base and Fully Hydraulic Tunnel Drilling Rig
  • A Portable Base and Fully Hydraulic Tunnel Drilling Rig

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0047] figure 1 It is a schematic structural diagram of the portable base 100 provided by the embodiment of the present invention.

[0048]The embodiment of the present invention provides a portable base 100, which includes a first horizontal bar 10, a sliding bar 11, a second horizontal bar 12 and a vertical bar,

[0049] The number of the first horizontal bars 10 is multiple, the multiple first horizontal bars 10 are parallel to each other, the vertical bars are set on two adjacent first horizontal bars 10, and are detachably connected with the first horizontal bars 10;

[0050] The sliding bar 11 is mounted on the first horizontal bar 10 and is slidably connected with the first horizontal bar 10, and the sliding bar 11 can slide along the direction of the first horizontal bar 10;

[0051] The second horizontal bar 12 is a contraction rod, which includes a plurality of contraction joints 121. The second horizontal bar is arranged on the sliding bar 11 and is connected with ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a portable base and a fully hydraulic tunnel drilling machine, which belongs to the field of geological exploration and drilling engineering. The portable base includes a first horizontal bar, a sliding bar, a second horizontal bar and a vertical bar. A plurality of first horizontal bars are parallel to each other, and the vertical bars are set on two adjacent first horizontal bars, and are detachably connected with the first horizontal bars. The sliding bar is set on the first horizontal bar and is slidably connected with the first horizontal bar, and the sliding bar can slide along the direction of the first horizontal bar. The second horizontal bar is a contraction rod, which includes a plurality of contraction joints. The second horizontal bar can expand and contract with the sliding of the sliding bar. The contraction joints are respectively provided with positioning holes, and the drilling machine and the positioning holes cooperate with each other to make the positioning of the drilling machine. The portable base is provided with a sliding bar that can be slidably connected on the first horizontal bar, so that the sliding bar can adjust the position of the sliding bar according to the different drilling rigs, so that the second horizontal bar connected to the sliding bar can be stretched. The positioning hole on the top can cooperate with the drilling machine for positioning.

Description

technical field [0001] The invention relates to the field of geological exploration and drilling engineering, in particular to a portable base and a fully hydraulic tunnel drilling rig. Background technique [0002] Fully hydraulic tunnel drilling rigs are generally used for underground construction in mines. The advantages are small size, convenient handling, and flexible construction angles. When the drilling rig is transferred from the underground to the surface construction, the traditional fixing method of the drilling rig is to build cement ground piles on the construction chassis, and use screws to connect the drilling rig and the cement ground piles for fixing. [0003] However, existing cement ground piles have limitations. 1. Construction time limitation. It takes a long time to build cement piles, and it takes an average of 2.5 days to move and install the drilling rig, including 1 day to wait for the cement to solidify, and 1 day to restore the site and clean t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21B15/00
CPCE21B15/00
Inventor 郎朋林宋建中高超赵建林张宝庆杨乐
Owner 内蒙古山金地质矿产勘查有限公司